Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Chandauli 164 582 120070 113319 94.38% 408 77
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 223 221 99.10
2 Pump House 223 216 96.86
3 Chlorination system 104 104 100.00
4 OHT 178 175/37 98.31
5 Distribution (Line Laying in Km.) 3479 3479 100.00
6 Solar Plant 117 112 95.73
7 F.H.T.C. 117097 110478 94.35
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2076 2039 98.22
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 582 303 52.06
12 Regular water supply 582 153 26.29