Sr.No. District City/Town Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost
Date of Start
Date of Comp. As per Agreement
Revised Date
Current Progress Component Wise Physical progress
Date of updation
Remark
Date of Sanction Sanction cost work Cost Centage O & M Cost Physical Progress(%) Financial Progress(Cr)
Work Component
No Of Component Capacity/Length/No Physical Progress(%) Photos
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Total -- -- -- 6128.20 2751.45 197.54 3160.11 38 1071.60 133 -- 4205.38 -- -- -- -- -- -- -- -- +0
28.06
-- -- --
1 Agra Agra Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 05-Apr-2023 04-Apr-2025
04-Apr-2025
+0.00
68.12
+0.00
150.22
Effluent Disposal Line (km.) 2 2.01 +0
97.50
12 28-May-2025
  • Component wise progress of Agra (HAM) 100 MLD STP- 68%, WIP 35 MLD STP- 76.2, WIP 31 MLD STP- 76.48%, WIP MPS 03 Nos.- 73%, WIP Rising Main 9.55 Km- 55%%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
  • As per pervious meeting discussion, In order to complete the remaining works of 31 MLD and 35 MLD STP and make them operational as per the prescribed timeline, Direction has been given to firm to complete the works as early as possible by increasing manpower.
  • As per pervious meeting discussion, In order to 07 Nos. DSTP forest clearance , Land Gazette notification meeting has been conducted on 02.05.2025 and soon gazette notification will be published and after that stage 2 permission will be applied
Intercepting Sewer (km) 3 1.94 +0
65.00
4
Interception And Diversion 1 22.00 +0
0.00
0
MPS (MLD) 3 373.50 +0
60.00
45
Rising main (mtr.) 3 8.97 +0
73.33
26
STP (MLD) 13 177.60 +0
21.08
75
2 Mathura Chhata Chhata Town Sewerage Scheme (I&D and STP works), District Mathura NGP DBOT 25-Oct-2022 56.15 34.52 2.23 19.40 1 6.00 14 M/s Shailesh Kumar J.V. 48.97 12-Nov-2024 11-Aug-2026 +0.00
5.00
+0.00
0.00
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 +0
0.00
0 28-May-2025
  • Date of Start 12.11.2024 has been given to the firm.
  • Structural drawing of STP approved from IIT and Preparation for piling work of SBR basin is in progress.
  • Survey and soil investigation has completed by firm.
  • BEP of STP has been approved.
  • Boundary wall construction work is going on at site.
  • Project is slightly delayed due to problem of water logging at STP Site as PWD, Mathura was constructing a culvert on Kosi Drain and due to diversion of drain the water of kosi drain got obstructed. The STP site is located near to the branch drain of kosi drain at upstream side which got over flowed and leading to water logging at STP Site
Intercepting Sewer (km) 1 2.17 +0
0.00
0
MPS (MLD) 1 13.50 +0
0.00
4
Nala Tapping Arrangement ( No.) 1 11.00 +0
0.00
0
Rising main (mtr.) 1 5.50 +0
0.00
4
STP (MLD) 1 6.00 +0
5.00
4
3 Mathura Vrindavan I&D and 13 MLD STP works at Vrindavan City NGP DBOT 25-Oct-2022 77.70 39.90 2.56 35.24 1 13.00 2 M/s SIMA -G D- N.P. (JV) 65.86 11-Jun-2024 10-Mar-2026 +0.00
44.92
+0.00
9.76
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 +0
49.00
0 28-May-2025
  • Work is going in SBR basin, CCT, Admin building, Pannel room, SHU and in MPS units.
  • Kalideh MPS rising main works has been done.
  • LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work is in progress.
Interception And Diversion 1 2.00 +0
2.00
0
MPS (MLD) 1 13.00 +0
20.00
4
Online Monitoring/LCS/MCS for proposed STPs and Ex 1 1.00 +0
0.00
0
Rising main (mtr.) 1 3.70 +0
69.00
0
STP (MLD) 1 13.00 +0
55.00
20
Treated water sump and associated works 1 1.00 +0
39.00
0
Upgradation of MPS 1 7.00 +0
2.00
0
4 Shamli Banat I&D and STP Work in Banat, Shamli NGP DBOT 25-May-2023 48.71 24.93 1.58 22.20 1 5.00 3 M/s R K Engineers Sales Ltd 37.92 14-Oct-2024 13-Jan-2026 +1.50
8.54
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 5.00 +0
0.00
0 02-Jun-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • BEP, Layout and HFD approved for 05 MLD STP.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • Approach Road and boundary wall work in progress
  • GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
Effluent Disposal Line (km.) 1 0.60 +0
0.00
0
Interception And Diversion 1 2.00 +0
0.00
0
MPS (MLD) 1 5.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 0.60 +0
0.00
0
STP (MLD) 1 5.00 +0
0.00
9
5 Shamli Bantikhera Banat I&D and STP Work in Bantikhera and Babri village, Shamli NGP DBOT 25-May-2023 55.47 29.41 1.84 24.22 1 5.00 1 M/s R K Engineers Sales Ltd 41.91 14-Oct-2024 13-Jan-2026 +0.00
5.00
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 5.00 +0
0.00
0 02-Jun-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • BEP, Layout and HFD approved for 05 MLD STP.
  • Work halted due to unresolved land dispute.
  • Project is 7 months behind schedule.
Effluent Disposal Line (km.) 1 0.40 +0
0.00
0
Interception And Diversion 1 4.00 +0
0.00
0
MPS (MLD) 1 6.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 2.00 +0
0.00
0
STP (MLD) 1 5.00 +0
0.00
4
6 Muzaffarnagar Muzzaffarnagar I&D and STP Work in Muzaffarnagar NGP HAM 13-Jan-2020 234.03 108.32 7.33 118.36 2 54.50 5 M/S Muzaffarnagar STP Pvt Ltd 205.09 04-Jun-2021 03-Jun-2023
30-Jun-2024
30-Sep-2024
31-Mar-2025
31-May-2025
+0.29
96.00
+4.21
146.00
Co-treatment Unit for Fecal Sludge (KLD) 2 100.00 +0
100.00
12 03-Jun-2025
  • 22 MLD STP Sahawali: Commercial Operation Date declared, Plant under O&M since 01.04.2024.
  • 32.5 MLD Kidwai Nagar: 02 Nos. I&D work completed, STP running by 02 I&D. IPS 2A work in progress.
Effluent Disposal Line (km.) 1 0.80 +0
100.00
15
Interception And Diversion 1 5.00 +0
100.00
12
IPS (MLD) 1 8.36 +0
100.00
8
MPS (MLD) 1 27.00 +0
100.00
8
Power Connection 1 2.00 +0
100.00
8
Rising main (mtr.) 1 2.40 +0
100.00
24
Sewer Line (km.) 1 1.48 +0
100.00
0
SPS (MLD) 2A 1 20.00 +0
90.00
19
STP (MLD) 2 54.50 +0
100.00
41
7 Shamli Shamli I&D and STP Work in Shamli NGP DBOT 25-May-2023 206.02 103.19 6.66 96.17 1 40.00 1 M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) 120.92 14-Oct-2024 13-Jan-2026 +1.40
9.97
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 20.00 +0
0.00
0 02-Jun-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Approach Road and Boundary wall work in progress
  • BEP, Layout and HFD approved for 40 MLD STP.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • GAD for Admin Building and Sludge Handling and Dewatering Building Submitted, which clear for Vetting & Structural Design.
  • CCT and I&D GAD Submitted, which clear for Vetting & Structural Design.
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
Effluent Disposal Line (km.) 1 0.10 +0
0.00
0
Interception And Diversion 1 1.00 +0
0.00
0
MPS (MLD) 1 40.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
7
Sewer Line (km.) 1 0.10 +0
0.00
0
STP (MLD) 1 40.00 +0
0.00
4
8 Shamli Thanabhawan I&D and STP Work in Thanabhawan, Shamli NGP DBOT 25-May-2023 97.19 55.63 3.50 38.06 1 10.00 5 M/s R K Engineers Sales Ltd 63.72 14-Oct-2024 13-Jan-2026 +1.00
7.66
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 10.00 +0
0.00
0 02-Jun-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • Approach Road work in progress
  • BEP, Layout and HFD approved for 10 MLD STP.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
  • CCT GAD were Submitted, which clear for Vetting & Structural Design.
  • Boundary Wall work in progress
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
Interception And Diversion 1 3.00 +0
0.00
0
MPS (MLD) 1 10.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 5600.00 +0
0.00
0
STP (MLD) 1 10.00 +0
0.00
8
9 Hapur Hapur I&D and STP works at District-Hapur NGP DBOT 19-Sep-2023 49.06 22.85 1.42 24.79 1 6.00 1 M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV) 39.28 08-Nov-2024 07-Feb-2026 +0.00
8.00
+0.00
0.00
Drains 1 1.00 +0
0.00
0 28-May-2025
  • Date of start is given on 08.11.24. Date of completion of work is 05.02.2026 to M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV), Reg. Office B-29, IIIrd Floor, RDC Rajnagar, Ghaziabad - 201013. AGREEMENT cost of project is Rs. 39,28,13,617.00.
  • Soil Testing Completed. Boundary Wall work is in progress.
  • The amount of mobilization advance has been claimed by the firm.
  • Land Issue Resolved in Feb 2025.
  • BEP has been submitted by the firm on 11.03.2025. The said BEP has been sent by this Division to the Executive Engineer, Division Office (E/M), Uttar Pradesh Jal Nigam (Rural), Meerut on 15.03.2025. After examining the components related to the equipment in the said office, some observations were found, the details of which have been made available to this Division by (E/M) letter no. 202/Hapur Sewerage/05 dated 05.05.2025. By letter no. 620/Yo-42/12 dated 13.05.2025 of this Division, the firm has been directed to provide revised BEP again.
MPS (MLD) 1 8.00 +0
0.00
4
STP (MLD) 1 6.00 +0
0.00
8
10 Hathras Hathras I&D and STP works at Hathras Town NGP DBOT 30-Jan-2023 128.91 70.48 4.55 53.88 1 24.00 10 M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd 119.05 06-Sep-2024 05-Jun-2026
05-Jun-2026
+0.00
5.00
+0.00
0.00
Admin Block 1 1.00 +0
0.00
0 28-May-2025
  • Date of start is 06.09.2024 and date of completion is 05.06.2024. Survey work is going on.
  • Survey and soil investigation has been completed by firm
  • Project was delayed as the land for STP was handed over in March 2025 by Nagar Palika Parishad Hathras. After that BEP is approved and structural drawings of SBR also vetted by IIT and at present excavation for SBR is in progress
Boundary wall (mtr.) 1 800.00 +0
0.00
0
Intercepting Sewer (km) 1 5.67 +0
0.00
0
MPS (MLD) 1 54.00 +0
0.00
0
Nala Tapping Arrangement ( No.) 1 8.00 +0
0.00
0
Rising main (mtr.) 1 0.13 +0
0.00
0
Staff Quarter type 2 1 1.00 +0
0.00
0
STP (MLD) 1 24.00 +0
5.00
4
11 Kanpur Nagar Kanpur Nagar I&D and STP works at Kanpur-Pankha NGP HAM 12-Mar-2018 967.23 248.39 31.05 718.84 1 30.00 3 M/s Kanpur River Management Pvt. Ltd. 708.70 11-Oct-2019 25-Oct-2021
29-Feb-2024
30-Apr-2025
30-Sep-2024
31-Aug-2024
31-Oct-2024
+0.00
100.00
+0.00
364.92
MPS (MLD) 1 115.00 +0
100.00
12 28-May-2025
  • Panka STP commissioned on dated 26.06.2023. Renovation of Jajmau work 95% complete.
O & M 3 295.00 +0
100.00
18
Sewer Line (km.) 1 16.00 +0
100.00
8
SPS (MLD) 2A 2 45.00 +0
100.00
18
STP (MLD) 1 30.00 +0
100.00
8
Upgradation of STP 1 130.00 +0
100.00
8
12 Mathura Kosi Kalan I&D and STP works at Kosi Kalan Town, District Mathura NGP DBOT 25-Oct-2022 66.59 31.24 2.03 33.32 1 12.00 1 M/s R K Engineers Sales Ltd 53.60 16-Oct-2024 15-Jul-2026 +0.00
5.00
+0.00
0.00
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 +0
0.00
0 28-May-2025
  • LOA has been issued on date 18.06.2024 and Date of start has been given 16.10.2024 to the firm. Survey work is going on
  • Survey and soil investigation has been done by firm.
  • Continous instruction has been given to firm for expediting the work.
  • BEP of STP has been approved.
  • Boundary wall construction work is going on at site.
  • Preparation for PCC work of SBR basin is in progress, hindered due to rain at site.
Intercepting Sewer (km) 1 0.03 +0
0.00
0
MPS (MLD) 1 12.00 +0
0.00
0
Nala Tapping Arrangement ( No.) 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
0
STP (MLD) 1 12.00 +0
5.00
8
13 Meerut Meerut I&D and STP works at Meerut NGP2-EAP HAM 06-May-2020 690.71 363.78 26.31 280.19 1 220.00 2 M/s. Meerut STP Pvt. Ltd. 369.74 11-Nov-2024 10-Nov-2026 +0.55
27.22
+0.00
89.24
Interception And Diversion 1 2.00 +0
0.00
0 02-Jun-2025
  • . Payment for1st and 2nd MS have been released
  • BEP, Layout and HFD approved for 220 MLD STP, 2 I&D’s & MPS, BEP of Treated Effluent Pipeline from Lohia Nagar STP to Outfall pending with Concessionaire, BEP of EPS and Pipeline pending with Concessionaire. GAD, Structural Design and Dwg. for Admin Building, SBR, CCT, Tonner Room approved QAP, Date Sheet and GAD of Decanter, Diffuser approved, QAP, Date Sheet and GAD of Air Blowers under review., Vortex Grit Remover approved by PE. GAD of Primary Clarifier approved by UPJN. , QAP, Date Sheet and GAD of Chlorination System pending with Concessionaire. QAP of Filter Belt Press pending with Concessionaire., Revised QAP of Pumps to be submitted by Concessionaire. Revised GAD of MPS pending with Concessionaire.
  • Work in progress at only 1 front of STP, Concessionaire need to open multiple working fronts. Inadequate Manpower deployment at site, Manpower deployment to be increased.
MPS 1 1.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
0
Sewer Line (km.) 1 0.56 +0
0.00
0
STP (MLD) 1 220.00 +0
0.00
19
14 Varanasi Varanasi I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi NGP DBOT 19-Oct-2022 308.09 97.62 7.81 172.94 1 55.00 2 M/s Enviro Infra Engineers limited MTS JV 151.55 07-Mar-2024 06-Dec-2025 +1.00
67.00
+0.00
38.50
Co-Treatment Facility(KLD) 1 10.00 +0
5.00
0 02-Jun-2025
  • Vetting of process flow of STP and MPS done by IIT-BHU. Structural drawing awaited. Preparatory works in progress
  • RCC framework of MCC, air blower, DG yard and transformer yard completed.
  • Laying of Rising main pipe line in progress
  • Laying of Effluent pipe line in progress
  • BEP submitted by firm to which observation have been raised. compliance pending.
  • Soil testing done. Team mobilized at site.
  • Meeting held under chairmanship of APD Sir on 20.06.2024 to resolve issues of design/drawing. Firm submitted BEP of STP only on 24.06.2024
  • Raft of SBR basin completed. Wall work in progress
Effluent Disposal Line (km.) 1 1.32 +0
28.00
13
IPS (MLD) 1 6.00 +0
33.00
20
MPS (MLD) 1 50.00 +0
52.00
19
Nala Tapping Arrangement ( No.) 1 2.00 +0
42.00
8
Rising main (mtr.) 1 2.10 +0
79.00
12
STP (MLD) 1 55.00 +0
81.00
22
15 Unnao Shuklaganj I&D of Drains and STP works in Shuklaganj (05MLD) NGP HAM 28-Jul-2017 65.18 25.93 1.90 37.35 1 5.00 5 M/s KRMPL Kanpur 38.87 11-Oct-2019 10-Jul-2021
10-Jul-2021
13-Jun-2023
14-Dec-2022
30-Apr-2025
30-Jun-2025
31-Aug-2024
31-Jan-2025
+0.00
84.00
+0.00
23.47
Boundary wall, staff quarter 1 526.00 +0
90.00
28 02-Jun-2025
  • Total 7 drains are discharging into River Ganga in NPP Shuklaganj out of which 5 drains of discharge 4.66 MLD has to be Intercepted & Diverted to under Construction 5 MLD STP Shuklaganj and rest of the 02 drains of discharge 7.3 MLD has to be tapped & treated by U.P. J.N. (Urban) under SBM 2 programme. There are 80 manpower required but 29 manpower engaged by KRMPL, for Civil work 25 manpower in different Structure PTU, Admin Building, Air Blower, & Boundary wall work and 04 manpower engaged in Electrical & Mechanical work Progress. Issue of cash flow constraint of concessionaire, Rs. 4.5 Cr. Fund required immediate to complete the balance work June-2025
Connecting Sewer 450mm 1 50.00 +0
99.00
12
Effluent Channel 1 100.00 +0
95.00
12
Interception & Diversion of Indra Nagar Drain (Nal 1 1.00 +0
95.00
28
MPS (8M dia, 20 MLD) 1 1.00 +0
77.00
24
Online Monitoring System for STP (1 inlet+1 outlet 1 2.00 +0
10.00
4
Rising Main (400mm dia DI K9) 1 100.00 +0
60.00
16
STP (MLD) 1 5.00 +0
85.00
16
16 Unnao Unnao I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 1 15.00 1 M/s KRMPL Kanpur 68.68 11-Oct-2019 10-Jul-2021
10-Jul-2021
15-Mar-2023
15-May-2025
15-Oct-2022
15-Sep-2021
25-Feb-2022
30-Apr-2023
30-Jun-2024
30-Jun-2025
30-May-2025
31-Dec-2024
31-Jul-2024
31-Mar-2025
+0.00
97.00
+0.00
52.01
Boundary wall, staff quarter 1 1.00 +0
0.00
36 02-Jun-2025
  • 200 mm RCC Pipe 315.30meter pipe laying out of 400 meter sewer line is done balance 84.17 meter work in progress, KRMPL deployed 12 manpower at site out of which. Dewatering & Cleaning of 543meter work in progress (350meter done) balance 193 meter work in progress KRMPL deployed cleaning of Sewer line 15manpower. STP 24 Hrs operating daily from 11.1.2025 through temporary line but CCT is not functional till date due to commissioning of CCT WORK IS PENDING from KRMPL also material short fall PAD HEATER & Pressure switch. Issue of cash flow constraint of concessionaire approx Rs. 2.00 Cr. Required to achieve the target in June-2025
Connecting Sewer 1100mm 1 3.20 +0
0.00
25
Effluent Channel 1 300.00 +0
0.00
28
Extra Item : Laying of 1200mm dia gravity sewer li 1 230.00 +0
0.00
16
Interception & Diversion of City Jail Drain (Nala 1 1.00 +0
0.00
29
MPS (15M dia 40MLD) 1 1.00 +0
0.00
28
Online Monitoring System for STP (1 inlet+1 outlet 1 1.00 +0
0.00
30
Rising Main (750mm dia) 1 100.00 +0
0.00
27
STP (MLD) 1 15.00 +0
0.00
25
17 Moradabad Moradabad Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 NGP HAM 23-Jul-2018 118.69 53.53 3.52 61.64 1 25.00 5 Moradabad STP Pvt Ltd 113.85 20-Jan-2023 19-Jan-2025
19-Jan-2025
+1.00
91.00
+0.00
54.19
Boundary wall 1 1.00 +0
92.00
8 02-Jun-2025
  • 03 milestones have been completed and 91% progress is achieved of project
  • EOT has been sent to NMCG for necessary perusal
  • Delay due to flooding condition at site due to back water from Ramganga river flooding
  • Deployment of Inadequate manpower at site, manpower deployment to be increased
  • Delay due to not starting work at multiple fronts
  • Payment of Electricity connection yet to be received
  • Completion of MPS plugging & inlet chamber due to high Sub-soil water level.
  • Meeting held under chairmanship of JMD sir on 06 may 2025 to expedite the progress on remaining structure & activity
Effluent Disposal Line (km.) 1 1.60 +0
69.00
8
Interception And Diversion 1 4.00 +0
94.00
12
MPS (MLD) 1 40.00 +0
85.00
20
Rising main (mtr.) 1 50.00 +0
0.00
0
Sewer Line (km.) 1 6.64 +0
98.00
13
STP (MLD) 1 25.00 +0
91.00
26
18 PrayagRaj Prayagraj Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 19-Mar-2024 18-Aug-2025 +0.51
57.77
+0.00
63.14
3 MLD Sitaram Ghat SPS 1 3.00 +0
0.00
4 02-Jun-2025
  • Basic Engineering Package has been vetted by IIT Delhi and same approved by UPJN (R)
  • GAD & RCC Design and Drawings of CCT, SBR Unit and Amitabh Bachhan Culvert SPS has been vetted by IIT Delhi and approved by UPJN (R)
  • RCC work for PTU is completed. Walk way and connecting channel is under Progress.
  • Outer wall of all SBR Basin of STP is completed up to 90 % and partian wall is under progress.
  • Casting of CCT Unit of STP is completed.
  • Casting of 7th Lift of Wall at AB Culvert SPS has been completed. Compound wall & Sinking work is under progress.
  • 2200 m laying of Rising main completed. Balance Laying is under progress.
  • TEPS Slab Casting work is under Progress.
  • Column work for Sludge Dewatering Unit and Slab for Sludge Sump is under progress.
  • Compound wall for Sitaram Ghat SPS is under Progress.
  • Pile Cap and Column work is under Progress for Admin Building.
  • Ground Floor Slab completed for STP Staff Quarter, Balance work is under Progress.
  • RCC work for MCC Room and Chlorination room is completed. RCC work for Air Blower and chlorine tonner yard is under Progress.
  • Work progress hampered due to site submergence from flood and Construction of newly proposed Gangapath Road along the river bank and heavy traffic congestion in view of Mahakumbh - 2025.
32 MLD AB Culvert SPS 1 32.00 +0
0.00
6
Effluent Disposal Line (km.) 1 0.30 +0
0.00
0
Effluent Pumping Station (MLD) 1 43.00 +0
0.00
0
Interception And Diversion 1 13.00 +0
0.00
0
Rehabilitation of Sewer Line 1 3.30 +0
0.00
0
Rising main (mtr.) 1 4070.00 +0
0.00
8
Sewer Line (km.) 1 2.16 +0
0.00
4
STP (MLD) 1 43.00 +0
0.00
47
19 PrayagRaj Prayagraj Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 27-Jan-2023 475.98 242.85 15.24 217.89 1 90.00 7 M/s Triveni Engineering and Industries 309.74 24-Aug-2024 23-Feb-2026 +1.00
31.00
+0.00
31.44
Effluent Disposal Line (km.) 1 0.30 +0
0.00
0 02-Jun-2025
  • Date of Start 24.08.2024 and Date of Completion 23.02.2026 including 3 month of Trial and run has been given to the firm M/s Triveni Engineering and Industries Limited.
  • Survey, Design and Drawing work is in progress
  • Excavation of SBR is completed & steel binding work is in progress.
  • Excavation of CCT is completed & steel binding work is in progress
  • Excavation & foundation work of workshop is completed, balance work is in progress.
  • Excavation & raft of TEPS completed, balance work is in progress.
  • 2500 m laying of Rising main completed. Balance Laying is under progress.
  • 300 m laying of Gravity main completed. Balance Laying is under progress.
  • Contract Agreement has been executed.
Effluent Pumping Station (MLD) 1 90.00 +0
0.00
0
Interception And Diversion 1 7.00 +0
0.00
0
Rehabilitation of Bund and Bund Road 1 1.00 +0
0.00
0
Rising main (mtr.) 1 3.45 +0
0.00
4
Sewer Line (km.) 1 4.20 +0
0.00
0
SPS (MLD) 2A 2 95.00 +0
0.00
0
STP (MLD) 1 90.00 +0
0.00
14
20 PrayagRaj Prayagraj Interception, Diversion of Balance discharge of 02 drains and 50 MLD STP to Augment existing Treatment Capacity (80 MLD) Naini STP for Sewerage District-A at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 05-Sep-2023 186.47 83.71 5.44 97.32 1 50.00 2 M/s JWIL-SSG (Joint Venture) 95.57 04-Mar-2025 03-Jul-2026 +0.00
2.52
+0.00
5.76
Co-treatment Unit for Fecal Sludge (KLD) 1 20.00 +0
0.00
0 02-Jun-2025
  • LOA issued to JV M/s JWIL and SSG ,New Delhi on 25.11.2024
  • LOA (Amended) issued to JV M/s JWIL and SSG , on dated 17.01.2025
  • Contract Agreement has been signed and Date of Start is 04.03.2025 and Date of Completion 03.07.2026 including 2 months Trial and Run Period
  • Survey, Design and Drawing work is in progress.
  • Soil testing of STP & SPS site has been completed.
  • BEP has been Submitted for 3.50 MLD Bargad Ghat SPS & Comments on the same is communicated to firm.
  • Firm has requested for amendment in proposed Technology of STP, the same has been rejected by NMCG, New Delhi vide letter no. Pr-12012/22/2022-Tech-1NMCG Dated 27.05.2025
Interception And Diversion 1 2.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
0
Sewer Line (km.) 1 0.06 +0
0.00
0
SPS (MLD) 2A 1 3.50 +0
0.00
0
STP (MLD) 1 50.00 +0
0.00
4
21 Mathura Mathura Mathura sewerage scheme (I&D and STP Works for balance drain) NGP2-NON EAP HAM 07-Sep-2022 292.56 149.85 9.61 133.10 1 60.00 4 M/s EIEL Mathura Infra Engineers Private Limited 240.01 30-Nov-2024 29-Nov-2026 +0.00
33.89
+0.00
22.85
Interception And Diversion 1 4.00 +0
15.00
0 27-May-2025
  • SBR basin and MPS construction work is in progress in STP premises.
  • IPS Kala Patthar civil work and its Rising main has been completed
  • LOA issued to L1 Bidder on on 27.09.2023. CA signed on 12.12.2023. Effective date of start shall be to concessionaire after financial closure.
  • Effective date of start has been given to concessionaire as 30.11.2024.
IPS (MLD) 2 47.00 +0
32.22
13
MPS (MLD) 1 60.00 +0
31.82
4
Rising main (mtr.) 1 9290.00 +0
74.73
4
STP (MLD) 1 60.00 +0
35.00
4
22 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 29-Jul-2024 240.93 123.45 6.97 110.51 2 42.50 2 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.90 07-Sep-2024 06-Jun-2026 +0.00
11.52
+0.00
107.85
Interception And Diversion 1 1.00 +0
3.00
0 27-May-2025
  • 39 MLD STP Daulatganj Operation & Maintenance started on dt. 05.11.2024.
  • Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Construction of Boundary wall work is in progress. SBR Basin-2 Seclector Zone wall 2nd lift reinforcement, shuttering and casting work is in progress. CCT wall reinforcement, shuttering and casting work is in progress. MPS - well curve reinforcement work is in progress.
MPS 1 3.50 +0
4.42
0
STP (MLD) 2 42.50 +0
59.58
23
Uppgradation of SPS 3 3.00 +0
100.00
0
23 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow NGP DBOT 30-Jan-2023 264.67 137.55 8.53 118.60 1 50.00 3 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.74 14-Jun-2024 13-Mar-2026 +0.00
3.49
+0.00
0.00
Interception And Diversion 1 3.00 +0
0.00
0 27-May-2025
  • Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed and handed over to UPJN (Urban). BEP of the STP is approved and design & drawing work is in progress. SBR Basin - Excavation, Dressing & Shoring work is in progress. Design & Drawing of proposed IPS is in progress.
Rising main (mtr.) 1 3.50 +0
0.00
0
SPS (MLD) 1 22.60 +0
0.00
0
STP (MLD) 1 50.00 +0
4.29
13
24 Ayodhya Faizabad Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) NGP HAM 06-May-2021 221.66 109.03 7.62 105.01 1 33.00 15 M/s Eco Protection Engineer Pvt Ltd 149.47 03-Mar-2023 02-Jan-2025
30-Sep-2024
31-Dec-2024
31-May-2024
+0.04
98.14
+0.00
86.86
Boundary wall (mtr.) 1 200.00 +0
99.90
4 03-Jun-2025
  • Trial run of 33 MLD STP is started.
Effluent Disposal Line (km.) 1 0.06 +0
99.80
4
MPS (MLD) 1 41.60 +0
99.60
4
Rising main (mtr.) 1 0.40 +0
100.00
4
Sewer Line (km.) 1 3.88 +0
98.75
4
STP (MLD) 1 33.00 +0
96.96
5