1 |
Lucknow |
Gomti |
Barikala Drain |
Untapped Drains |
1.80 |
Construction of Boundary wall and PCC work of SBR Basin is in progress. |
24-Mar-2025 11:16 AM |
2 |
Lucknow |
Gomti |
Fazullaiganj Downstream |
Untapped Drains |
0.77 |
Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed . BEP of the project is approved. Design & Drawing work is progress. |
19-Feb-2025 04:11 PM |
3 |
Lucknow |
Gomti |
Fazullaiganj Upstream |
Untapped Drains |
8.96 |
Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed . BEP of the project is approved. Design & Drawing work is progress. |
19-Feb-2025 04:11 PM |
4 |
Lucknow |
Gomti |
Gomti Nagar Drain |
Untapped Drains |
22.15 |
DPR has been submitted to NMCG vide letter no. 1050/0369/SMCG-UP/12 dt. 27.09.2022 for approval. CE (Ganga) again requested to SMCG for approval of DPR on dt.19.06.2024. |
04-Dec-2024 01:57 PM |
5 |
Lucknow |
Gomti |
Gomti Nagar Extension Drain |
Untapped Drains |
2.07 |
DPR has been submitted to NMCG vide letter no. 1050/0369/SMCG-UP/12 dt. 27.09.2022 for approval. CE (Ganga) again requested to SMCG for approval of DPR on dt.19.06.2024. |
04-Dec-2024 01:57 PM |
6 |
Lucknow |
Gomti |
Maheshganj |
Untapped Drains |
8.22 |
Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed . BEP of the project is approved. Design & Drawing work is progress. |
19-Feb-2025 04:12 PM |
7 |
Lucknow |
Gomti |
Sahara City Drain |
Untapped Drains |
7.59 |
DPR has been submitted to NMCG vide letter no. 1050/0369/SMCG-UP/12 dt. 27.09.2022 for approval. CE (Ganga) again requested to SMCG for approval of DPR on dt.19.06.2024. |
04-Dec-2024 01:57 PM |