Drains Details

S.No District River Drain Name Drain Type Total Discharge (MLD) Remarks Last Update Date
1 Lucknow Gomti Barikala Drain Untapped Drains 1.80 Construction of Boundary wall and PCC work of SBR Basin is in progress. 24-Mar-2025 11:16 AM
2 Lucknow Gomti Fazullaiganj Downstream Untapped Drains 0.77 Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed . BEP of the project is approved. Design & Drawing work is progress. 19-Feb-2025 04:11 PM
3 Lucknow Gomti Fazullaiganj Upstream Untapped Drains 8.96 Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed . BEP of the project is approved. Design & Drawing work is progress. 19-Feb-2025 04:11 PM
4 Lucknow Gomti Gomti Nagar Drain Untapped Drains 22.15 DPR has been submitted to NMCG vide letter no. 1050/0369/SMCG-UP/12 dt. 27.09.2022 for approval. CE (Ganga) again requested to SMCG for approval of DPR on dt.19.06.2024. 04-Dec-2024 01:57 PM
5 Lucknow Gomti Gomti Nagar Extension Drain Untapped Drains 2.07 DPR has been submitted to NMCG vide letter no. 1050/0369/SMCG-UP/12 dt. 27.09.2022 for approval. CE (Ganga) again requested to SMCG for approval of DPR on dt.19.06.2024. 04-Dec-2024 01:57 PM
6 Lucknow Gomti Maheshganj Untapped Drains 8.22 Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed . BEP of the project is approved. Design & Drawing work is progress. 19-Feb-2025 04:12 PM