1 |
Mau |
Ghaghara |
Drain No. 10 (Ward-10) |
Untapped Drains |
0.29 |
DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.03.2025 |
20-Feb-2025 03:54 PM |
2 |
Mau |
Ghaghara |
Drain No. 4 (Ward-4) |
Untapped Drains |
1.76 |
DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.03.2025 |
20-Feb-2025 03:55 PM |
3 |
Mau |
Ghaghara |
Durga Mata Mandir drain |
Untapped Drains |
0.09 |
DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.03.2025 |
20-Feb-2025 03:54 PM |
4 |
Mau |
Ghaghara |
Kabristan drain |
Untapped Drains |
0.03 |
DPR for construction of FSTP is being prepared as directed by NMCG |
01-Jul-2024 12:00 AM |
5 |
Mau |
Ghaghara |
Mukti dham drain |
Untapped Drains |
0.04 |
DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.03.2025 |
20-Feb-2025 03:53 PM |