Drains Details

S.No District River Drain Type Total Discharge (MLD) Remarks
1 Sant Kabeer Nagar Aami Untapped Drains 2.10 CSAP has been approved in SBM 2.0 SLTC meeting dt. 05.09.22 and SHPSC meeting dated 20.09.22. DPR is under preparation. As an interim measure, a project for construction of 32 KLD FSTP at Maghar under State Sector is under progress. FSTP is under trial-ru
2 Sant Kabeer Nagar Aami Untapped Drains CSAP has been approved in SBM 2.0 SLTC meeting dt. 05.09.22 and SHPSC meeting dated 20.09.22. DPR is under preparation. As an interim measure, a project for construction of 32 KLD FSTP at Maghar under State Sector is under progress. FSTP is under trial-ru
3 Sant Kabeer Nagar Aami Untapped Drains 6.80 CSAP has been approved in SBM 2.0 SLTC meeting dt. 05.09.22 and SHPSC meeting dated 20.09.22. DPR is under preparation. As an interim measure, a project for construction of 32 KLD FSTP at Khalilabad under State Sector is under progress. FSTP is under tria