1 |
Shamli |
Krishni |
Babari - Banti Kheda Nala |
Untapped Drains |
3.00 |
BEP, Layout and HFD approved for 05 MLD STP. work is haulted due land issue. |
09-Jun-2025 05:19 PM |
2 |
Shamli |
Krishni |
Near Bada Buda Talab (Drain No. 01) |
Untapped Drains |
1.40 |
BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:20 PM |
3 |
Shamli |
Krishni |
Near bus stand at Charthawal Road (Drain No. 04) |
Untapped Drains |
3.20 |
BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:21 PM |
4 |
Shamli |
Krishni |
Near dumping site (Drain No. 05) |
Untapped Drains |
0.50 |
BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:21 PM |
5 |
Shamli |
Krishni |
Near Karaunda Road (Drain No. 02) |
Untapped Drains |
1.60 |
BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:17 PM |
6 |
Shamli |
Krishni |
Near Krishni River Overbridge (Drain No. 03) |
Untapped Drains |
0.20 |
BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:20 PM |
7 |
Shamli |
Krishni |
Near Muzaffarnagar Road (Drain No. 01) |
Untapped Drains |
1.01 |
BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:17 PM |
8 |
Shamli |
Krishni |
Near Shamli Adda (Drain No. 02) |
Untapped Drains |
1.40 |
BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:20 PM |
9 |
Shamli |
Krishni |
Near Shamshanghat (Drain No. 03) |
Untapped Drains |
0.46 |
BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:18 PM |
10 |
Shamli |
Krishni |
Shamli Nala |
Untapped Drains |
20.10 |
BEP, Layout and HFD approved for 40 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Admin Building and Sludge Handling and Dewatering Building Submitted, which clear for Vetting & Structural Design. CCT and I&D GAD Submitted, which clear for Vetting & Structural Design. Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:18 PM |