1 |
Unnao |
Ganga |
City Jail Drain (Dakari drain) |
Tapped Drains |
11.36 |
? 1200 mm RCC Pipe 360.80meter pipe laying out of 399.80 meter sewer line is done balance 39.00meter work in progress, KRMPL deployed 18 manpower at site. Dewatering & Cleaning of 543.45meter work in progress (538.45meter done) balance 05.00meter work in progress KRMPL deployed cleaning of Sewer line 15manpower. STP operating daily from 11.1.2025 through temporary line but CCT is not functional till date due to commissioning of CCT WORK IS PENDING from KRMPL also material short fall PAD HEATER & Pressure switch. Issue of cash flow constraint of concessionaire, Rs. 2.0 Cr. Fund required immediate to complete the balance work Dec-2025 |
07-Jul-2025 12:27 PM |
2 |
Unnao |
Ganga |
Ganga Vishnu Drain |
Untapped Drains |
0.10 |
I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec-25 |
07-Jul-2025 12:28 PM |
3 |
Unnao |
Ganga |
Indira Nagar Drain |
Untapped Drains |
2.80 |
I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec-25 |
25-Jun-2025 02:26 PM |
4 |
Unnao |
Ganga |
Manohar Nagar Nala IInd (New) |
Untapped Drains |
0.57 |
I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec-25 |
25-Jun-2025 02:27 PM |
5 |
Unnao |
Ganga |
Manohar Nagar Nala Ist (New) |
Untapped Drains |
0.63 |
I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec-25 |
25-Jun-2025 02:26 PM |
6 |
Unnao |
Ganga |
Railway Bridge Drain |
Untapped Drains |
0.56 |
I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec-25 |
25-Jun-2025 02:26 PM |
7 |
Unnao |
Ganga |
Ravidas Nagar Nala (New) |
Untapped Drains |
1.30 |
Tender is under process by UPJN(U) under SBM 2.0) |
25-Jun-2025 02:26 PM |
8 |
Unnao |
Ganga |
Srinagar Drain |
Untapped Drains |
6.00 |
Tender is under process by UPJN(U) under SBM 2.0) |
25-Jun-2025 02:26 PM |