S.No District River Drain Name Drain Type Total Discharge (MLD) Remarks Last Update Date
1 Unnao Ganga City Jail Drain (Dakari drain) Tapped Drains 11.36 1200 mm RCC Pipe 374.80meter pipe laying out of 399.80 meter sewer line is done balance 25.00meter work in progress, KRMPL deployed 18 manpower at site. Dewatering & Cleaning of 543.45meter work in done KRMPL deployed cleaning of Sewer line 15manpower. STP operating daily from 11.1.2025 through temporary line but CCT is not functional till date due to commissioning of CCT WORK IS PENDING from KRMPL also material short fall PAD HEATER & Pressure switch. Issue of cash flow constraint of concessionaire, Rs. 2.0 Cr. Fund required immediate to complete the balance work Dec-2025 14-Jul-2025 10:31 AM