Drains Details

S.No District River Drain Name Drain Type Total Discharge (MLD) Remarks Last Update Date
1 Unnao Ganga City Jail Drain (Dakari drain) Tapped Drains 11.36 STP 4-6 Hrs operating daily receiving average discharge 4MLD from 07.11.2023 through temporary line. Gravity main sewer line de-silting work till date 2.885 km. sewer line has been cleaned out of total 3.2 km. Cleaning of 0.315 km sewer line is balance till date. From two week KRMPL not deployed manpower at site for cleaning of Sewer line 22-Jul-2024 09:51 AM