Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Cirtified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Ambedkar Nagar 509 1299 236727 91.38% 259046 493 131
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 511 509 99.61
2 Pump House 511 507 99.22
3 Chlorination system 92 92 100.00
4 OHT 509 506/101 99.41
5 Distribution (Line Laying in Km.) 10207 9835 96.36
6 Solar Plant 508 460 90.55
7 F.H.T.C. 26604442 22724602 85.42
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 3439 3365 97.85
10 Villages where 100 % road restoration completed 96810 50388 52.05