Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Ghazipur 412 1029 152631 130818 85.71% 55 6
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 421 398 94.54
2 Pump House 421 331 78.62
3 Chlorination system 80 80 100.00
4 OHT 412 344/20 83.50
5 Distribution (Line Laying in Km.) 5082 3835 75.46
6 Solar Plant 254 105 41.34
7 F.H.T.C. 152631 130818 85.71
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 1457 1363 93.55
10 Villages where 100 % road restoration completed 97065 58910 60.69
11 Comissioning of Village 1029 207 20.12
12 Regular water supply 1029 196 19.05