Sr.No. | Components | Target | Achivement | % |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 783 | 780 | 99.62 |
2 | Pump House | 783 | 761 | 97.19 |
3 | Chlorination system | 432 | 420 | 97.22 |
4 | OHT | 782 | 779/322 | 99.62 |
5 | Distribution (Line Laying in Km.) | 9831 | 9644 | 98.10 |
6 | Solar Plant | 629 | 562 | 89.35 |
7 | F.H.T.C. | 554464 | 528306 | 95.28 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 2238 | 2184 | 97.59 |
10 | Villages where 100 % road restoration completed | 97064 | 59914 | 61.73 |
11 | Comissioning of Village | 1078 | 664 | 61.60 |
12 | Regular water supply | 1078 | 644 | 59.74 |
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | GA INFRA-VPL | 162 | 209 | 87614 | 74738 | 85.30% | 27 | 0 |
2 | PNC-SPML-JV | 598 | 869 | 338020 | 325498 | 96.30% | 326 | 172 |
Total | 760 | 1078 | 425634 | 400236 | 94.03% | 353 | 172 |