Components Wise Physical Progress |
||||
---|---|---|---|---|
Sr.No. | Components | Target | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 31 | 31 | 100.00 |
2 | Pump House | |||
3 | Chlorination system | |||
4 | OHT | 196 | 196/196 | 100.00 |
5 | Distribution (Line Laying in Km.) | 6123 | 6123 | 99.99 |
6 | Solar Plant | |||
7 | F.H.T.C. | 268964 | 268434 | 99.80 |
8 | W.T.P. | 2 | 2 | 100.00 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 1271 | 1254 | 98.66 |
10 | Villages where 100 % road restoration completed | 97065 | 58821 | 60.60 |
11 | Comissioning of Village | |||
12 | Regular water supply |