Sr.No. | Components | Target | Achivement | % |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 913 | 912 | 99.89 |
2 | Pump House | 913 | 909 | 99.56 |
3 | Chlorination system | 746 | 679 | 91.02 |
4 | OHT | 899 | 892/442 | 99.22 |
5 | Distribution (Line Laying in Km.) | 7656 | 7290 | 95.22 |
6 | Solar Plant | 889 | 868 | 97.64 |
7 | F.H.T.C. | 516742 | 487628 | 94.37 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 3443 | 3405 | 98.90 |
10 | Villages where 100 % road restoration completed | 97064 | 59914 | 61.73 |
11 | Comissioning of Village | 1943 | 1700 | 87.49 |
12 | Regular water supply | 1943 | 1706 | 87.80 |
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | LC INFRA | 301 | 632 | 155508 | 153645 | 98.80% | 564 | 149 |
2 | Vindhya-GAJA (JV) | 606 | 1311 | 307348 | 281894 | 91.72% | 730 | 103 |
Total | 907 | 1943 | 462856 | 435539 | 94.10% | 1294 | 252 |