Jal Jeevan Mission - District Dashboard


Heirarchy / District Progress Reference
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Scheme Details Phase 1       Phase 2,3,5       Phase 4       Jal Nigam
JJM Scheme :
O&M Schemes:
JJM Village :
Jal Nigam Scheme :
Jal Nigam Village :
JJM + Jal Nigam Scheme :
JJM + Jal Nigam Village :
Automation Details
Integrated Scheme :
Integrated OHT :
Integrated Village :
Automation Verify Schemes Details
Integrated Scheme :
Integrated OHT :
Integrated Village :
Water Demand (Meter 3)
Daily :
Weekly :
Monthly :
Water Supply (Meter 3)
Daily :
Weekly :
Monthly :
Village Status
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
NGO :
NTD :
Incoming Complaints/Feedback Received
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken Details
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Total Pradhan Call Feedback
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
S.E.,(Division), Jal Nigam (Rural) Feedback Taken
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (Zone), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (H.O.), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Unit Co-ordinator (Technical), SWSM
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 913 912 99.89
2 Pump House 913 909 99.56
3 Chlorination system 746 679 91.02
4 OHT 899 892/442 99.22
5 Distribution (Line Laying in Km.) 7656 7290 95.22
6 Solar Plant 889 868 97.64
7 F.H.T.C. 516742 487628 94.37
9 ROAD DISMENTLING/RESTORATION(KM) 3443 3405 98.90
10 Villages where 100 % road restoration completed 97064 59914 61.73
11 Comissioning of Village 1943 1700 87.49
12 Regular water supply 1943 1706 87.80
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 LC INFRA 301 632 155508 153645 98.80% 564 149
2 Vindhya-GAJA (JV) 606 1311 307348 281894 91.72% 730 103
Total 907 1943 462856 435539 94.10% 1294 252
;