Jal Jeevan Mission - District Dashboard


Heirarchy / District Progress Reference
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Scheme Details Phase 1       Phase 2,3,5       Phase 4       Jal Nigam
JJM Scheme :
O&M Schemes:
JJM Village :
Jal Nigam Scheme :
Jal Nigam Village :
JJM + Jal Nigam Scheme :
JJM + Jal Nigam Village :
Automation Details
Integrated Scheme :
Integrated OHT :
Integrated Village :
Automation Verify Schemes Details
Integrated Scheme :
Integrated OHT :
Integrated Village :
Water Demand (Meter 3)
Daily :
Weekly :
Monthly :
Water Supply (Meter 3)
Daily :
Weekly :
Monthly :
Village Status
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
NGO :
NTD :
Incoming Complaints/Feedback Received
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken Details
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Total Pradhan Call Feedback
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
S.E.,(Division), Jal Nigam (Rural) Feedback Taken
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (Zone), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (H.O.), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Unit Co-ordinator (Technical), SWSM
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 804 792 98.51
2 Pump House 804 775 96.39
3 Chlorination system 254 232 91.34
4 OHT 776 762/324 98.20
5 Distribution (Line Laying in Km.) 7534 6807 90.35
6 Solar Plant 702 508 72.36
7 F.H.T.C. 432496 424257 98.10
9 ROAD DISMENTLING/RESTORATION(KM) 2112 2052 97.16
10 Villages where 100 % road restoration completed 97064 59914 61.73
11 Comissioning of Village 1500 657 43.80
12 Regular water supply 1500 621 41.40
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Gayatri Projects LTD 217 326 79973 78754 98.48% 233 43
2 LC INFRA 365 714 154235 152178 98.67% 458 127
3 Rithwik-Koya (JV) 213 460 69826 67133 96.14% 104 41
4 UNIVERSAL MEP 69 118 22593 20950 92.73% 44 12
Total 864 1618 326627 319015 97.67% 839 223
;