Sr.No. | Components | Target | Achivement | % |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 390 | 389 | 99.74 |
2 | Pump House | 390 | 359 | 92.05 |
3 | Chlorination system | 123 | 106 | 86.18 |
4 | OHT | 349 | 348/142 | 99.71 |
5 | Distribution (Line Laying in Km.) | 3885 | 3690 | 94.98 |
6 | Solar Plant | 339 | 324 | 95.58 |
7 | F.H.T.C. | 239209 | 228727 | 95.62 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 1253 | 1226 | 97.85 |
10 | Villages where 100 % road restoration completed | 97064 | 59914 | 61.73 |
11 | Comissioning of Village | 540 | 192 | 35.56 |
12 | Regular water supply | 540 | 177 | 32.78 |
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | Indian Hume Pipe | 94 | 159 | 45516 | 44123 | 96.94% | 90 | 48 |
2 | OMIL-JWIL (JV) | 259 | 381 | 140330 | 131323 | 93.58% | 37 | 4 |
Total | 353 | 540 | 185846 | 175446 | 94.40% | 127 | 52 |