Components Wise Physical Progress |
||||
---|---|---|---|---|
Sr.No. | Components | Target | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 467 | 464 | 99.36 |
2 | Pump House | 467 | 459 | 98.29 |
3 | Chlorination system | 318 | 273 | 85.85 |
4 | OHT | 407 | 403/202 | 99.02 |
5 | Distribution (Line Laying in Km.) | 4395 | 4333 | 98.59 |
6 | Solar Plant | 416 | 407 | 97.84 |
7 | F.H.T.C. | 304114 | 290678 | 95.58 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 1948 | 1896 | 97.33 |
10 | Villages where 100 % road restoration completed | 97064 | 59859 | 61.67 |
11 | Comissioning of Village | 810 | 571 | 70.49 |
12 | Regular water supply | 810 | 540 | 66.67 |
Agency Progress Details |
||||||||
---|---|---|---|---|---|---|---|---|
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | Vindhya-GAJA (JV) | 308 | 610 | 176838 | 164029 | 92.76% | 414 | 104 |
2 | VSA | 116 | 200 | 65230 | 64873 | 99.45% | 176 | 46 |
Total | 424 | 810 | 242068 | 228902 | 94.56% | 590 | 150 |