Jal Jeevan Mission-District Dashboard

Heirarchy / District Progress
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Scheme Details
JJM Scheme :
JJM Village :
Jal Nigam Scheme :
Jal Nigam Village :
JJM + Jal Nigam Scheme :
JJM + Jal Nigam Village :
Village Status
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
NGO :
NTD :
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 NCC Ltd. 376 663 219867 213006 96.88% 350 182
Total 376 663 219867 213006 96.88% 350 182
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 442 439 99.32
2 Pump House 442 437 98.87
3 Chlorination system 424 414 97.64
4 OHT 381 378/188 99.21
5 Distribution (Line Laying in Km.) 4940 4839 97.96
6 Solar Plant 374 363 97.06
7 F.H.T.C. 250572 243037 96.99
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2318 2301 99.27
10 Villages where 100 % road restoration completed 97065 58819 60.60
11 Comissioning of Village 663 629 94.87
12 Regular water supply 663 623 93.97
;