Jal Jeevan Mission-District Dashboard

Heirarchy / District Progress
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Scheme Details
JJM Scheme :
JJM Village :
Jal Nigam Scheme :
Jal Nigam Village :
JJM + Jal Nigam Scheme :
JJM + Jal Nigam Village :
Village Status
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
NGO :
NTD :
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 GA INFRA-VPL 199 510 83571 77736 93.02% 245 45
2 KLSR - RAYS (JV) 113 319 43759 36292 82.94% 45 13
3 LC INFRA 219 488 96947 88057 90.83% 215 69
Total 531 1317 224277 202085 90.11% 505 127
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 574 563 98.08
2 Pump House 574 546 95.12
3 Chlorination system 169 150 88.76
4 OHT 536 523/152 97.57
5 Distribution (Line Laying in Km.) 8141 7499 92.11
6 Solar Plant 528 372 70.45
7 F.H.T.C. 264424 235594 89.10
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2142 2106 98.32
10 Villages where 100 % road restoration completed 97065 58819 60.60
11 Comissioning of Village 1317 499 37.89
12 Regular water supply 1317 435 33.03
;