Sr.No. | Components | Target | Achivement | % |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 980 | 943 | 96.22 |
2 | Pump House | 980 | 872 | 88.98 |
3 | Chlorination system | 462 | 445 | 96.32 |
4 | OHT | 795 | 775/484 | 97.48 |
5 | Distribution (Line Laying in Km.) | 14344 | 12979 | 90.48 |
6 | Solar Plant | 667 | 587 | 88.01 |
7 | F.H.T.C. | 491476 | 450049 | 91.57 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 5234 | 5197 | 99.29 |
10 | Villages where 100 % road restoration completed | 97064 | 59914 | 61.73 |
11 | Comissioning of Village | 1766 | 555 | 31.43 |
12 | Regular water supply | 1766 | 292 | 16.53 |
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | JMC - Lakshmi (JV) | 366 | 760 | 184343 | 168379 | 91.34% | 348 | 49 |
2 | Power Mech Projects Ltd | 456 | 1006 | 223096 | 209850 | 94.06% | 529 | 36 |
Total | 822 | 1766 | 407439 | 378229 | 92.83% | 877 | 85 |