Components Wise Physical Progress |
||||
---|---|---|---|---|
Sr.No. | Components | Target | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 664 | 657 | 98.95 |
2 | Pump House | 664 | 640 | 96.39 |
3 | Chlorination system | 210 | 210 | 100.00 |
4 | OHT | 662 | 530/202 | 80.06 |
5 | Distribution (Line Laying in Km.) | 11581 | 10748 | 92.81 |
6 | Solar Plant | 543 | 430 | 79.19 |
7 | F.H.T.C. | 651466 | 490223 | 75.25 |
8 | W.T.P. | |||
9 | ROAD DISMENTLING/RESTORATION(KM) | 3935 | 3894 | 98.96 |
10 | Villages where 100 % road restoration completed | 97065 | 58842 | 60.62 |
11 | Comissioning of Village | 1338 | 417 | 31.17 |
12 | Regular water supply | 1338 | 409 | 30.57 |