Sr.No. | Components | Target | Achivement | % |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 710 | 701 | 98.73 |
2 | Pump House | 710 | 698 | 98.31 |
3 | Chlorination system | 250 | 163 | 65.20 |
4 | OHT | 708 | 697/202 | 98.45 |
5 | Distribution (Line Laying in Km.) | 5931 | 5432 | 91.59 |
6 | Solar Plant | 489 | 468 | 95.71 |
7 | F.H.T.C. | 468258 | 440271 | 94.02 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 2341 | 2141 | 91.46 |
10 | Villages where 100 % road restoration completed | 97064 | 59914 | 61.73 |
11 | Comissioning of Village | 1111 | 923 | 83.08 |
12 | Regular water supply | 1111 | 350 | 31.50 |
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | GA INFRA - BABA (JV) | 251 | 391 | 142356 | 127790 | 89.77% | 153 | 33 |
2 | Gayatri Projects LTD | 127 | 187 | 72074 | 70973 | 98.47% | 126 | 56 |
3 | NKG-PRIMUS (JV) | 327 | 533 | 162008 | 150910 | 93.15% | 152 | 27 |
Total | 705 | 1111 | 376438 | 349673 | 92.89% | 431 | 116 |