Jal Jeevan Mission - District Dashboard


Heirarchy / District Progress Reference
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Scheme Details Phase 1       Phase 2,3,5       Phase 4       Jal Nigam
JJM Scheme :
O&M Schemes:
JJM Village :
Jal Nigam Scheme :
Jal Nigam Village :
JJM + Jal Nigam Scheme :
JJM + Jal Nigam Village :
Automation Details
Integrated Scheme :
Integrated OHT :
Integrated Village :
Automation Verify Schemes Details
Integrated Scheme :
Integrated OHT :
Integrated Village :
Water Demand (Meter 3)
Daily :
Weekly :
Monthly :
Water Supply (Meter 3)
Daily :
Weekly :
Monthly :
Village Status
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
NGO :
NTD :
Incoming Complaints/Feedback Received
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken Details
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Total Pradhan Call Feedback
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
S.E.,(Division), Jal Nigam (Rural) Feedback Taken
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (Zone), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (H.O.), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Unit Co-ordinator (Technical), SWSM
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 302 297 98.34
2 Pump House 302 275 91.06
3 Chlorination system 128 119 92.97
4 OHT 290 282/122 97.24
5 Distribution (Line Laying in Km.) 4486 3899 86.91
6 Solar Plant 283 158 55.83
7 F.H.T.C. 186084 179596 96.51
9 ROAD DISMENTLING/RESTORATION(KM) 1202 1164 96.84
10 Villages where 100 % road restoration completed 97064 59914 61.73
11 Comissioning of Village 451 286 63.41
12 Regular water supply 451 274 60.75
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 GA INFRA-VPL 165 233 80224 76042 94.79% 26
2 Larsen & Toubro Ltd 124 218 78878 77443 98.18% 137 78
Total 289 451 159102 153485 96.47% 163 78
;