| Sr. No. | Name of Town/District | Name of STP | Project Name | Design Technology | Capacity of STP (MLD) | Design Parameter | Inlet Parameter | Outlet Parameter | Influent (MLD) | %age Utilization | Agency Maintaining the STP | Functional / Non-Functional | Compliant / Non-Compliant | Updation Date | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| BOD | TSS | BOD | COD | TSS | BOD | COD | TSS | ||||||||||||
| 1 | Prayagraj | Kodra | 1. Sewerage & Non-Sewerage schemes for Pollution abatement of River Ganga at District-'B' & 'E' of AllahabadSewerage & Non-Sewerage schemes for Pollution abatement of River Ganga at District-'B' & 'E' of Allahabad - 85 MLD | HRBF | 25.00 | <20 | <30 | 135 | 328 | 261 | 13 | 36 | 21 | 25.47 MLD | 102% | M/s Prayagraj Water Pvt. Ltd. (Adani) | Functional | Compliant | 17-04-2021 |
| 2 | Prayagraj | Numayadih | HRBF | 50.00 | <20 | <30 | 135 | 320 | 264 | 15 | 40 | 28 | 9.94 | 20% | M/s Prayagraj Water Pvt. Ltd. (Adani) | Functional | Compliant | 22-05-2021 | |
| 3 | Prayagraj | Ponghat | 10.00 | <20 | <30 | 132 | 296 | 248 | 15 | 40 | 23 | 7.134 | 71% | Prayagraj Water Pvt. Ltd. (Adani) | Functional | Compliant | 06-05-2021 | ||
| 4 | Prayagraj | Naini - 2 | 2. Sewerage & Non-Sewerage schemes for Pollution abatement of River Ganga at District-'A' of Allahabad | ASP | 20.00 | <30 | <50 | 163 | 360 | 335 | 19 | 36 | 35 | 15.68 MLD | 78% | M/s Prayagraj Water Pvt. Ltd. (Adani) | Functional | Compliant | 22-05-2021 |
| 5 | Prayagraj | Salori - 2 | 3. 14 mld STP at Salori, Allahabad | SBR | 14.00 | <10 | <10 | 104.4 | 271 | 257 | 7 | 20.2 | 7.2 | 14.449 | 103% | M/S Toshiba water solutions prayagraj | Functional | Compliant | 12-06-2021 |
| 6 | Varanasi | Varanasi GAP-II (JICA) | 4. JICA assisted Ganga Action Plan Phase-II Project at Varanasi (EAP - JICA) Construction of 140 MLD STP at Dinapur | ASP | 140.00 | 20 | 30 | 105 | 223 | 198 | 14 | 30 | 20 | 81.32 | 58% | VA-Tech Wabag | Functional | Compliant | 25-05-2021 |
| 7 | Garhmukteshwar | Garhmukteshwar-I (NGRBA) | 5. Sewerage system & STP works - 9 MLD | UASB | 6.00 | < 20 | <30 | 184 | 227 | 195 | 14 | 45 | 17 | 3.45 | 58% | M/S Anandilal lalpuria | Functional | Compliant | 18-05-2021 |
| 8 | Garhmukteshwar | Garhmukteshwar-II (NGRBA) | UASB | 3.00 | < 20 | <30 | 176 | 196 | 185 | 10 | 55 | 18 | .50 | 17% | M/S Anandilal lalpuria | Functional | Compliant | 18-05-2021 | |
| 9 | Moradabad | Moradabad (NGRBA) | 6. Sewerage system & STP works (Phase I ) | UASB | 58.00 | < 10 | < 10 | 135 | 310.5 | 260 | 6.0 | 28.8 | 8.5 | 26.9MLD | 46% | L&T; | Functional | Compliant | 14-03-2021 |
| 10 | Kannauj | Kannauj (State/ NGRBA) | 7. Sewerage system & STP works (Phase II) | SBR | 13.00 | <10 | <10 | 109 | 290 | 286 | 8 | 74 | 9 | 9 | 69% | UPJN | Functional | Compliant | 10-06-2021 |
| 11 | Narora | Narora (NGRBA) | 8. Sewerage scheme at Narora, Bulandshar | UASB | 4.00 | < 10 | <30 | 149 | 293 | 290 | 4.98 | 25.2 | 25.1 | 2.256 | 56% | M/S EMS Infracon | Functional | Compliant | 06-06-2021 |
| 12 | Anupshahar | Anupshahar (NGRBA) Zone A | 9. Sewerage Works in Anup Shahar, Buland Shahar - 2.5 MLD | UASB | 1.50 | < 10 | < 10 | 189 | 270 | 305 | 10 | 32 | 10 | 1.489 | 99% | LC Infra Projects P Ltd. | Functional | Compliant | 06-06-2021 |
| 13 | Anupshahar | Anupshahar | MBBR | 1.00 | < 10 | < 10 | 123 | 284 | 208 | 8 | 18 | 8 | 47.8 | 4780% | Functional | Compliant | 03-06-2021 | ||
| 14 | Bithoor | Bithoor STP | 10. Sewerage scheme and STP at Bithoor Kanpurnagar, (UP) | - | 2.40* | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | NGRBA | Functional | Non-Compliant | 03-06-2021 | ||
| 347.9 | 293.188 | 84% | |||||||||||||||||