Sr.No. | Components | Target | Achivement | % |
---|---|---|---|---|
1 | 2 | 3 | 4 | 5 |
4 | OHT | 136 | 136/127 | 100.00 |
5 | Distribution (Line Laying in Km.) | 4221 | 4115 | 97.50 |
7 | F.H.T.C. | 163961 | 163698 | 99.84 |
8 | W.T.P. | 3 | 3 | 100.00 |
9 | ROAD DISMENTLING/RESTORATION(KM) | 448 | 367 | 81.92 |
10 | Villages where 100 % road restoration completed | 97064 | 59914 | 61.73 |
Sr.No. | Agency | No Of Scheme | No Of Village | households | FHTC | FHTC % | Har Gar Gal | Certified |
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
1 | GVPR | 1 | 69 | 19570 | 19570 | 100.00% | 69 | 43 |
2 | Larsen & Toubro Ltd | 2 | 345 | 98082 | 98039 | 99.96% | 343 | 107 |
Total | 3 | 414 | 117652 | 117609 | 99.96% | 412 | 150 |