Jal Jeevan Mission-District Dashboard

Heirarchy / District Progress
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Scheme Details
JJM Scheme :
JJM Village :
Jal Nigam Scheme :
Jal Nigam Village :
JJM + Jal Nigam Scheme :
JJM + Jal Nigam Village :
Village Status
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
NGO :
NTD :
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 LC INFRA 210 267 126286 119978 95.00% 80 55
2 NKG-PRIMUS (JV) 393 684 192424 156783 81.48% 50 28
Total 603 951 318710 276761 86.84% 130 83
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 602 600 99.67
2 Pump House 602 600 99.67
3 Chlorination system 266 223 83.83
4 OHT 601 599/175 99.67
5 Distribution (Line Laying in Km.) 5044 4876 96.67
6 Solar Plant 486 409 84.16
7 F.H.T.C. 350056 308083 88.01
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2259 2192 97.03
10 Villages where 100 % road restoration completed 97065 58819 60.60
11 Comissioning of Village 951 559 58.78
12 Regular water supply 951 535 56.26
;