Sr.No. District City/Town Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost
Date of Start
Date of Comp. As per Agreement
Revised Date
Current Progress Component Wise Physical progress
Date of updation
Remark
Reason for Delay
Action taken for delay
Tentative date for inauguration
Tentative Zero Discharge Date
Date of Sanction Sanction cost work Cost Centage O & M Cost Physical Progress(%) Financial Progress(Cr)
Work Component
No Of Component Capacity/Length/No Physical Progress(%) Photos
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Total -- -- -- 5894.17 2643.13 190.21 3041.75 36 1017.10 128 -- 4000.29 -- -- -- -- -- -- -- -- +0
33.09
-- -- -- -- -- -- --
1 Agra Agra Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 05-Apr-2023 04-Apr-2025
04-Apr-2025
31-Dec-2025
+0.32
69.91
+0.00
150.22
Effluent Disposal Line (km.) 2 2.01 +0
45.00
12 30-Jun-2025
  • As per pervious meeting discussion, In order to 07 Nos. DSTP forest clearance , Land Gazette notification meeting has been conducted on 02.05.2025 and soon gazette notification will be published and after that stage 2 permission will be applied
  • Component wise progress of Agra (HAM) 100 MLD STP- 68%, WIP 35 MLD STP- 76.2, WIP 31 MLD STP- 76.48%, WIP MPS 03 Nos.- 73%, WIP Rising Main 9.55 Km- 55%%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
  • As per pervious meeting discussion, In order to complete the remaining works of 31 MLD and 35 MLD STP and make them operational as per the prescribed timeline, Direction has been given to firm to complete the works as early as possible by increasing manpower.
NOC Land for 07 NOs. DSTP, Risin 1st Stage Permission was granted from forest department and 2nd stage permission is under process. A request was made by District Magistrate proposal sent to Revenue department UP Lucknow for 1 No. DSTP Indira Memorial. In current laying of rising main and intercepting sewer line permission was granted by district administration and work is under progress. MPS Nagla Buri public hindrance was resolved work is under progress. 01-Nov-2026 01-Sep-2026
Intercepting Sewer (km) 3 1.94 +0
72.33
4
Interception And Diversion 1 22.00 +0
0.00
0
MPS (MLD) 3 373.50 +0
61.67
45
Rising main (mtr.) 3 8.97 +0
76.00
26
STP (MLD) 13 177.60 +0
22.15
75
2 Mathura Chhata Chhata Town Sewerage Scheme (I&D and STP works), District Mathura NGP DBOT 25-Oct-2022 56.15 34.52 2.23 19.40 1 6.00 14 M/s Shailesh Kumar J.V. 48.97 12-Nov-2024 11-Aug-2026 +0.02
5.20
+0.00
0.00
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 +0
0.00
0 30-Jun-2025
  • Structural drawing of STP approved from IIT and Preparation for piling work of SBR basin is in progress.
  • Date of Start 12.11.2024 has been given to the firm.
  • Survey and soil investigation has completed by firm.
  • BEP of STP has been approved.
  • Boundary wall construction work is going on at site.
  • Project is slightly delayed due to problem of water logging at STP Site as PWD, Mathura was constructing a culvert on Kosi Drain and due to diversion of drain the water of kosi drain got obstructed. The STP site is located near to the branch drain of kosi drain at upstream side which got over flowed and leading to water logging at STP Site
Project is slightly delayed due to problem of water logging at STP Site as PWD, Mathura was constructing a culvert on Kosi Drain and due to diversion of drain the water of kosi drain got obstructed. The STP site is located near to the branch drain of kosi drain at upstream side which got over flowed and leading to water logging at STP Site. Communication has been done to PWD and Irrigation Department for the problem of water logging at site. Additionally firm has been instructed to take preventive measures and initiate the work. Now the Piling and associated work has been commenced at site for SBR basin. 12-Aug-2026 12-Aug-2026
Intercepting Sewer (km) 1 2.17 +0
0.00
0
MPS (MLD) 1 13.50 +0
0.50
4
Nala Tapping Arrangement ( No.) 1 11.00 +0
0.00
0
Rising main (mtr.) 1 5.50 +0
0.00
4
STP (MLD) 1 6.00 +0
5.18
4
3 Mathura Vrindavan I&D and 13 MLD STP works at Vrindavan City NGP DBOT 25-Oct-2022 77.70 39.90 2.56 35.24 1 13.00 2 M/s SIMA -G D- N.P. (JV) 65.86 11-Jun-2024 10-Mar-2026 +2.08
51.48
+0.00
9.76
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 +0
55.00
0 30-Jun-2025
  • LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work is in progress.
  • Work is going in SBR basin, CCT, Admin building, Pannel room, SHU and in MPS units.
  • Kalideh MPS rising main works has been done.
Initially preliminary work at Site got hindered due to start of monsoon just after the date of start of the project. Firm has started the work after the monsoon and currently the work is being going on almost on all fronts by the firm. The progress is being regularly expedited by firm to complete the work on scheduled date. - 11-Mar-2026 11-Mar-2026
Interception And Diversion 1 2.00 +0
0.00
0
MPS (MLD) 1 13.00 +0
60.00
4
Online Monitoring/LCS/MCS for proposed STPs and Ex 1 1.00 +0
0.00
0
Rising main (mtr.) 1 3.70 +0
69.00
0
STP (MLD) 1 13.00 +0
60.00
20
Treated water sump and associated works 1 1.00 +0
60.00
0
Upgradation of MPS 1 7.00 +0
0.00
0
4 Shamli Banat I&D and STP Work in Banat, Shamli NGP DBOT 25-May-2023 48.71 24.93 1.58 22.20 1 5.00 3 M/s R K Engineers Sales Ltd 37.92 14-Oct-2024 13-Jan-2026 +0.50
10.34
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 5.00 +0
3.00
0 30-Jun-2025
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • Approach Road and boundary wall work in progress
  • GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • BEP, Layout and HFD approved for 05 MLD STP.
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
Firm delayed submission of desig Liquidity Damage (L.D.) imposed on firm for delay. 24-Apr-2026 14-Apr-2026
Effluent Disposal Line (km.) 1 0.60 +0
0.00
0
Interception And Diversion 1 2.00 +0
0.00
0
MPS (MLD) 1 5.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 0.60 +0
0.00
0
STP (MLD) 1 5.00 +0
13.90
13
5 Shamli Bantikhera Banat I&D and STP Work in Bantikhera and Babri village, Shamli NGP DBOT 25-May-2023 55.47 29.41 1.84 24.22 1 5.00 1 M/s R K Engineers Sales Ltd 41.91 14-Oct-2024 13-Jan-2026 +0.00
5.00
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 5.00 +0
3.00
0 30-Jun-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Project is 7 months behind schedule.
  • Survey and Soil investigation work completed
  • BEP, Layout and HFD approved for 05 MLD STP.
  • Work halted due to unresolved land dispute.
Due to land dispute Letters has been written to the District Administration requesting their intervention to resolve the dispute with the nearby farmers. 24-Apr-2026 14-Aug-2026
Effluent Disposal Line (km.) 1 0.40 +0
0.00
0
Interception And Diversion 1 4.00 +0
0.00
0
MPS (MLD) 1 6.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 2.00 +0
0.00
0
STP (MLD) 1 5.00 +0
8.00
9
6 Shamli Shamli I&D and STP Work in Shamli NGP DBOT 25-May-2023 206.02 103.19 6.66 96.17 1 40.00 1 M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) 120.92 14-Oct-2024 13-Jan-2026 +0.00
11.50
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 20.00 +0
3.00
0 30-Jun-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • CCT and I&D GAD Submitted, which clear for Vetting & Structural Design.
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • Approach Road and Boundary wall work in progress
  • BEP, Layout and HFD approved for 40 MLD STP.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • GAD for Admin Building and Sludge Handling and Dewatering Building Submitted, which clear for Vetting & Structural Design.
Firm delayed submission of desig Liquidity Damage (L.D.) imposed on firm for delay. 24-Apr-2026 14-Apr-2026
Effluent Disposal Line (km.) 1 0.10 +0
0.00
0
Interception And Diversion 1 1.00 +0
5.00
0
MPS (MLD) 1 40.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
7
Sewer Line (km.) 1 0.10 +0
0.00
0
STP (MLD) 1 40.00 +0
13.50
8
7 Shamli Thanabhawan I&D and STP Work in Thanabhawan, Shamli NGP DBOT 25-May-2023 97.19 55.63 3.50 38.06 1 10.00 5 M/s R K Engineers Sales Ltd 63.72 14-Oct-2024 13-Jan-2026 +0.00
8.29
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 10.00 +0
3.00
0 30-Jun-2025
  • Project is 4 months behind schedule.
  • Delay in design/drawing submission by Contractor.
  • Contractor need to increase expedite the progress of work and submission of design/drawings.
  • GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
  • GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
  • CCT GAD were Submitted, which clear for Vetting & Structural Design.
  • Approach Road work in progress
  • BEP, Layout and HFD approved for 10 MLD STP.
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed
  • Boundary Wall work in progress
Firm delayed submission of desig Liquidity Damage (L.D.) imposed on firm for delay. 24-Apr-2026 14-Apr-2026
Interception And Diversion 1 3.00 +0
0.00
0
MPS (MLD) 1 10.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 5600.00 +0
0.00
0
STP (MLD) 1 10.00 +0
12.50
12
8 Hapur Hapur I&D and STP works at District-Hapur NGP DBOT 19-Sep-2023 49.06 22.85 1.42 24.79 1 6.00 1 M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV) 39.28 08-Nov-2024 07-Feb-2026 +0.00
8.00
+0.00
0.00
Drains 1 1.00 +0
0.00
0 25-Jun-2025
  • Date of start is given on 08.11.24. Date of completion of work is 05.02.2026 to M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV), Reg. Office B-29, IIIrd Floor, RDC Rajnagar, Ghaziabad - 201013. AGREEMENT cost of project is Rs. 39,28,13,617.00.
  • Soil Testing Completed. Boundary Wall work is in progress.
  • The amount of mobilization advance has been claimed by the firm.
  • Land Issue Resolved in Feb 2025.
  • BEP has been submitted by the firm on 11.03.2025. The said BEP has been sent by this Division to the Executive Engineer, Division Office (E/M), Uttar Pradesh Jal Nigam (Rural), Meerut on 15.03.2025. After examining the components related to the equipment in the said office, some observations were found, the details of which have been made available to this Division by (E/M) letter no. 202/Hapur Sewerage/05 dated 05.05.2025. By letter no. 620/Yo-42/12 dated 13.05.2025 of this Division, the firm has been directed to provide revised BEP again.
  • Revised BEP has been submitted by the firm on 06.06.2025. The said BEP has been sent by this Division to the Executive Engineer, Division Office (E/M), Uttar Pradesh Jal Nigam (Rural), Meerut on 09.06.2025
  • BEP and GAD sent for vetting to IIT BHU VARANASI on 19.06.25
01-Jan-1900 01-Jan-1900
MPS (MLD) 1 8.00 +0
2.00
4
Others 1 1.00 +0
6.00
0
STP (MLD) 1 6.00 +0
0.00
8
9 Hathras Hathras I&D and STP works at Hathras Town NGP DBOT 30-Jan-2023 128.91 70.48 4.55 53.88 1 24.00 10 M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd 119.05 06-Sep-2024 05-Jun-2026
05-Jun-2026
+0.00
5.55
+0.00
0.00
Admin Block 1 1.00 +0
0.00
0 30-Jun-2025
  • Survey and soil investigation has been completed by firm
  • Project was delayed as the land for STP was handed over in March 2025 by Nagar Palika Parishad Hathras. After that BEP is approved and structural drawings of SBR also vetted by IIT and at present excavation for SBR is in progress
  • Date of start is 06.09.2024 and date of completion is 05.06.2024. Survey work is going on.
Land issued by NPP Project Manager personally contacted the District Magistrate and requested to remove the potato crop, on which the District Magistrate talked to the Executive Officer over telephone and directed to remove the potato crop within 7 working days. As per the instructions of the District Magistrate, the construction work of STP could be started in the month of March 2025 after removing the potato crop from the land provided by the Executive Officer Municipal Council Hathras 05-Jun-2026
Boundary wall (mtr.) 1 800.00 +0
0.00
0
Intercepting Sewer (km) 1 5.67 +0
0.00
0
MPS (MLD) 1 54.00 +0
0.00
0
Nala Tapping Arrangement ( No.) 1 8.00 +0
0.00
0
Rising main (mtr.) 1 0.13 +0
0.00
0
Staff Quarter type 2 1 1.00 +0
0.00
0
STP (MLD) 1 24.00 +0
5.55
4
10 Kanpur Nagar Kanpur Nagar I&D and STP works at Kanpur-Pankha NGP HAM 12-Mar-2018 967.23 248.39 31.05 718.84 1 30.00 3 M/s Kanpur River Management Pvt. Ltd. 708.70 11-Oct-2019 11-Oct-2021
29-Feb-2024
30-Apr-2025
30-Jun-2025
30-Sep-2024
31-Aug-2024
31-Jul-2025
31-Oct-2024
+0.00
99.45
+0.00
364.92
MPS (MLD) 1 115.00 +0
100.00
12 24-Jun-2025
  • Panka STP commissioned on dated 24.06.2023. Renovation of 130 MLD STP Jajmau work 95% complete.
Project delayed due to poor management by the firm. Liquidity Damage (L.D.) imposed on firm for delay. 01-Jan-1900 01-Mar-2027
O & M 3 295.00 +0
100.00
18
Sewer Line (km.) 1 16.00 +0
100.00
8
SPS (MLD) 2A 2 45.00 +0
100.00
18
STP (MLD) 1 30.00 +0
100.00
8
Upgradation of STP 1 130.00 +0
95.00
8
11 Mathura Kosi Kalan I&D and STP works at Kosi Kalan Town, District Mathura NGP DBOT 25-Oct-2022 66.59 31.24 2.03 33.32 1 12.00 1 M/s R K Engineers Sales Ltd 53.60 16-Oct-2024 15-Jul-2026 +0.05
5.25
+0.00
0.00
Ancilliary works(Admin building,staff quarter ,roa 1 1.00 +0
0.00
0 30-Jun-2025
  • Continous instruction has been given to firm for expediting the work.
  • BEP of STP has been approved.
  • Survey and soil investigation has been done by firm.
  • LOA has been issued on date 18.06.2024 and Date of start has been given 16.10.2024 to the firm. Survey work is going on
  • Boundary wall construction work is going on at site.
  • Preparation for PCC work of SBR basin is in progress, hindered due to rain at site.
Firm has taken additional time in initial document submission and ULB's continuous waste disposal at project site also hindered the work. Letter had been written to ULB to stop waste disposal at site. It was stopped and site was cleared for the work. Additionally notices/letters has been written to the firm for expediting the progress. Now the firm has been expedited the work and SBR basin work is in progress. 16-Jul-2026 16-Jul-2026
Intercepting Sewer (km) 1 0.03 +0
0.00
0
MPS (MLD) 1 12.00 +0
5.25
0
Nala Tapping Arrangement ( No.) 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
0
STP (MLD) 1 12.00 +0
0.00
8
12 Meerut Meerut I&D and STP works at Meerut NGP2-EAP HAM 06-May-2020 690.71 363.78 26.31 280.19 1 220.00 2 M/s. Meerut STP Pvt. Ltd. 369.74 11-Nov-2024 10-Nov-2026 +0.36
29.02
+0.00
89.24
Interception And Diversion 1 2.00 +0
10.00
0 30-Jun-2025
  • Work in progress at only 1 front of STP, Concessionaire need to open multiple working fronts. Inadequate Manpower deployment at site, Manpower deployment to be increased.
  • . Payment for1st and 2nd MS have been released
  • BEP, Layout and HFD approved for 220 MLD STP, 2 I&D’s & MPS, BEP of Treated Effluent Pipeline from Lohia Nagar STP to Outfall pending with Concessionaire, BEP of EPS and Pipeline pending with Concessionaire. GAD, Structural Design and Dwg. for Admin Building, SBR, CCT, Tonner Room approved QAP, Date Sheet and GAD of Decanter, Diffuser approved, QAP, Date Sheet and GAD of Air Blowers under review., Vortex Grit Remover approved by PE. GAD of Primary Clarifier approved by UPJN. , QAP, Date Sheet and GAD of Chlorination System pending with Concessionaire. QAP of Filter Belt Press pending with Concessionaire., Revised QAP of Pumps to be submitted by Concessionaire. Revised GAD of MPS pending with Concessionaire.
No Delay No Delay 21-Feb-2027 11-Feb-2027
MPS 1 1.00 +0
10.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
15.00
0
Sewer Line (km.) 1 0.56 +0
10.00
0
STP (MLD) 1 220.00 +0
34.90
24
13 Varanasi Varanasi I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi NGP DBOT 19-Oct-2022 308.09 97.62 7.81 172.94 1 55.00 2 M/s Enviro Infra Engineers limited MTS JV 151.55 07-Mar-2024 06-Dec-2025 +1.00
71.00
+12.72
51.22
Co-Treatment Facility(KLD) 1 10.00 +0
20.00
0 25-Jun-2025
  • Laying of Effluent pipe line in progress
  • BEP submitted by firm to which observation have been raised. compliance pending.
  • Soil testing done. Team mobilized at site.
  • Meeting held under chairmanship of APD Sir on 20.06.2024 to resolve issues of design/drawing. Firm submitted BEP of STP only on 24.06.2024
  • Vetting of process flow of STP and MPS done by IIT-BHU. Structural drawing awaited. Preparatory works in progress
  • Raft of SBR basin completed. Wall work in progress
  • RCC framework of MCC, air blower, DG yard and transformer yard completed.
  • Laying of Rising main pipe line in progress
No delay No delay 15-Jan-2026 06-May-2026
Effluent Disposal Line (km.) 1 1.32 +0
50.00
17
IPS (MLD) 1 6.00 +0
43.00
20
MPS (MLD) 1 50.00 +0
56.00
23
Nala Tapping Arrangement ( No.) 1 2.00 +0
76.00
8
Rising main (mtr.) 1 2.10 +0
82.00
12
STP (MLD) 1 55.00 +0
83.00
26
14 Unnao Shuklaganj I&D of Drains and STP works in Shuklaganj (05MLD) NGP HAM 28-Jul-2017 65.18 25.93 1.90 37.35 1 5.00 5 M/s KRMPL Kanpur 38.87 11-Oct-2019 10-Jul-2021
10-Jul-2021
13-Jun-2023
14-Dec-2022
30-Apr-2025
30-Aug-2025
30-Jun-2025
31-Aug-2024
31-Dec-2025
31-Jan-2025
+0.00
84.00
+0.00
23.47
Boundary wall, staff quarter 1 526.00 +0
90.00
32 30-Jun-2025
  • Total 7 drains are discharging into River Ganga in NPP Shuklaganj out of which 5 drains of discharge 4.66 MLD has to be Intercepted & Diverted to under Construction 5 MLD STP Shuklaganj and rest of the 02 drains of discharge 7.3 MLD has to be tapped & treated by U.P. J.N. (Urban) under SBM 2 programme. There are 80 manpower required but 67 manpower engaged by KRMPL, for Civil work 51 manpower in different Structure PTU, Admin Building, Air Blower, & Boundary wall work and 16 manpower engaged in Electrical & Mechanical work Progress. Issue of cash flow constraint of concessionaire, Rs. 4.5 Cr. Fund required immediate to complete the balance work Dec-2025
The scheme is based on Hybrid Annuity Mode (HAM), 40% of the work cost was to be paid by NMCG, 40% by the lending bank (Bank Lender) and 20% was to be borne by the executing firm, but due to KRMPL not receiving loan from any bank for Hybrid Annuity Mode (HAM) works and the progress of works being affected by the unavailability of required resources/laborers and machinery by KRMPL, the firm was continuously directed to increase the availability of necessary resources such as laborers and machinery at the work site and complete the scheme within the stipulated time period, but the firm orally cited its financial conditions and did not increase the resources at the work site, due to which the work could not be completed within the stipulated time limit. Due to delays in completing the work, a penalty of Rs. 38.72 lacs has also been imposed on the concessionaire M/s K.R.M.P.L., Kanpur, and show cause notices have been issued to the responsible firm by the undersigned and senior officers for unnecessary delays in completing the work. 31-Dec-2025 30-Dec-2025
Connecting Sewer 450mm 1 50.00 +0
99.00
16
Effluent Channel 1 100.00 +0
95.00
16
Interception & Diversion of Indra Nagar Drain (Nal 1 1.00 +0
95.00
32
MPS (8M dia, 20 MLD) 1 1.00 +0
77.00
28
Online Monitoring System for STP (1 inlet+1 outlet 1 2.00 +0
10.00
4
Rising Main (400mm dia DI K9) 1 100.00 +0
60.00
20
STP (MLD) 1 5.00 +0
85.00
16
15 Unnao Unnao I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 1 15.00 1 M/s KRMPL Kanpur 68.68 11-Oct-2019 10-Jul-2021
10-Jul-2021
15-Mar-2023
15-May-2025
15-Oct-2022
15-Sep-2021
25-Feb-2022
30-Apr-2023
30-Jun-2024
30-Jun-2025
30-May-2025
31-Dec-2024
31-Dec-2025
31-Jul-2024
31-Mar-2025
31-Oct-2025
+0.00
97.00
+0.00
52.01
Boundary wall, staff quarter 1 1.00 +0
90.00
43 30-Jun-2025
  • 1200 mm RCC Pipe 335.30meter pipe laying out of 399.80 meter sewer line is done balance 64.50meter work in progress, KRMPL deployed 18 manpower at site. Dewatering & Cleaning of 543.45meter work in progress (510meter done) balance 33.45meter work in progress KRMPL deployed cleaning of Sewer line 15manpower. STP operating daily from 11.1.2025 through temporary line but CCT is not functional till date due to commissioning of CCT WORK IS PENDING from KRMPL also material short fall PAD HEATER & Pressure switch
The scheme is based on Hybrid Annuity Mode (HAM), 40% of the work cost was to be paid by NMCG, 40% by the lending bank (Bank Lender) and 20% was to be borne by the executing firm, but due to KRMPL not receiving loan from any bank for Hybrid Annuity Mode (HAM) works and the unavailability of necessary resources/labor and machinery by KRMPL, the progress of the work was affected, for which the firm was continuously directed to increase the availability of necessary resources i.e. labor and machinery at the work site and to complete the scheme within the stipulated time period, but the firm verbally cited its financial situation and did not increase any resources at the work site, due to which the work could not be completed within the stipulated time frame. Due to the delay in completing the work by the concessionaire firm M/s K.R.M.P.L., Kanpur, a financial penalty of Rs. 55.91 Lacs has also been imposed on the firm. Furthermore, a show cause notice has been issued to the executing firm by both the undersigned and higher authorities for unnecessary delay in completing the work. 31-Oct-2025 31-Oct-2025
Connecting Sewer 1100mm 1 3.20 +0
92.00
25
Effluent Channel 1 300.00 +0
96.00
32
Extra Item : Laying of 1200mm dia gravity sewer li 1 230.00 +0
100.00
20
Interception & Diversion of City Jail Drain (Nala 1 1.00 +0
98.00
33
MPS (15M dia 40MLD) 1 1.00 +0
98.00
32
Online Monitoring System for STP (1 inlet+1 outlet 1 1.00 +0
90.00
30
Rising Main (750mm dia) 1 100.00 +0
96.00
31
STP (MLD) 1 15.00 +0
96.00
29
16 Moradabad Moradabad Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 NGP HAM 23-Jul-2018 118.69 53.53 3.52 61.64 1 25.00 5 Moradabad STP Pvt Ltd 113.85 20-Jan-2023 19-Jan-2025
19-Jan-2025
30-Jun-2025
+0.50
92.00
+0.00
54.19
Boundary wall 1 1.00 +0
92.00
8 30-Jun-2025
  • Delay due to not starting work at multiple fronts
  • Payment of Electricity connection yet to be received
  • Completion of MPS plugging & inlet chamber due to high Sub-soil water level.
  • Meeting held under chairmanship of JMD sir on 06 may 2025 to expedite the progress on remaining structure & activity
  • EOT has been sent to NMCG for necessary perusal
  • Delay due to flooding condition at site due to back water from Ramganga river flooding
  • Deployment of Inadequate manpower at site, manpower deployment to be increased
  • Review meeting under chairmanship of MD sir on dated 28.05.2025 were held to expedite work
  • 03 milestones have been completed and 92% progress is achieved of project
The progress of the work was affected, for which the firm was continuously directed to increase the availability of necessary resources i.e. labor and machinery at the work site Liquidated damages of Rs.5,94,000.00 has been proposed. 31-Dec-2025 31-Jul-2025
Effluent Disposal Line (km.) 1 1.60 +0
97.00
8
Interception And Diversion 1 4.00 +0
94.00
12
MPS (MLD) 1 40.00 +0
86.00
20
Rising main (mtr.) 1 50.00 +0
0.00
0
Sewer Line (km.) 1 6.64 +0
98.00
13
STP (MLD) 1 25.00 +0
92.00
26
17 PrayagRaj Prayagraj Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 19-Mar-2024 18-Aug-2025 +1.62
60.16
+0.00
66.21
3 MLD Sitaram Ghat SPS 1 3.00 +0
26.00
4 30-Jun-2025
  • Basic Engineering Package has been vetted by IIT Delhi and same approved by UPJN (R)
  • GAD & RCC Design and Drawings of CCT, SBR Unit and Amitabh Bachhan Culvert SPS has been vetted by IIT Delhi and approved by UPJN (R)
  • RCC work for PTU is completed. Walk way and connecting channel is under Progress.
  • RCC work for MCC Room ,Chlorination room & Air Blower is completed. RCC work for chlorine tonner yard is under Progress.
  • Outer wall of all SBR Basin of STP is completed up to 90 % and partian wall is under progress.
  • RCC of CCT Unit of STP is completed.
  • Casting of 9th Lift of Wall at AB Culvert SPS has been completed. Compound wall & Sinking work is under progress.
  • 2200 m laying of Rising main completed. Balance Laying is under progress
  • TEPS Slab Casting work is completed .Brick work and plaster is under Progress
  • Slab work for Sludge Dewatering Unit is under progress.
  • Compound wall for Sitaram Ghat SPS is under Progress.
  • Column work is under Progress for Admin Building.
  • Ground Floor and 1st Floor Slab completed for STP Staff Quarter. Balance work is under Progress
Progress has been hampered due to Mahakumbh-2025, Construction of River front road and site submergence during monsoon. 01-Jan-1900 01-Jan-1900
32 MLD AB Culvert SPS 1 32.00 +0
55.00
6
Effluent Disposal Line (km.) 1 0.30 +0
5.00
0
Effluent Pumping Station (MLD) 1 43.00 +0
59.00
4
Interception And Diversion 1 13.00 +0
5.00
0
Rehabilitation of Sewer Line 1 3.30 +0
0.00
0
Rising main (mtr.) 1 4070.00 +0
56.00
8
Sewer Line (km.) 1 2.16 +0
5.00
4
STP (MLD) 1 43.00 +0
68.00
70
18 PrayagRaj Prayagraj Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 27-Jan-2023 475.98 242.85 15.24 217.89 1 90.00 7 M/s Triveni Engineering and Industries 309.74 24-Aug-2024 23-Feb-2026 +2.00
35.00
+0.00
31.44
Effluent Disposal Line (km.) 1 0.30 +0
0.00
0 30-Jun-2025
  • Contract Agreement has been executed.
  • Date of Start 24.08.2024 and Date of Completion 23.02.2026 including 3 month of Trial and run has been given to the firm M/s Triveni Engineering and Industries Limited.
  • Survey, Design and Drawing work is in progress
  • 2770 m laying of Rising main completed. Balance Laying is under progress.
  • 675 m laying of Gravity main completed. Balance Laying is under progress
  • Excavation, PCC, Grit Slab and Wall Raft of SBR & Wall 1st Lift is completed & Wall 2nd Lift is in progress.
  • Excavation, PCC and Raft of CCT is completed & steel binding work of Wall is in progress
  • Excavation, foundation and column work up to lintel level of workshop is completed, balance work is in progress
  • Excavation & raft of TEPH completed & 1st lift of Wall is completed. Balance work is in progress
  • Earth work, PCC, Footing foundation work of Air Blower Building is completed and balance work is in progress.
  • Earth work 95% completed of Inlet Chamber is and balance PCC work is in progress.
  • Shifting of Existing Rising main inside Mumfordganj SPS Campus work is in progress.
  • Excavation, PCC and Raft of CCT is completed & steel binding work of Wall is in progress.
  • Survey, Design and Drawing work is in progress
  • Excavation, PCC, Grit Slab and Wall Raft of SBR is completed & Wall 1st Lift is in progress.
Progress has been hampered due to Mahakumbh-2025, Construction of River front road and site submergence during monsoon. 01-Jan-1900 01-Jan-1900
Effluent Pumping Station (MLD) 1 90.00 +0
0.00
0
Interception And Diversion 1 7.00 +0
0.00
0
MPS (MLD) 2 95.00 +0
0.00
0
Rehabilitation of Bund and Bund Road 1 1.00 +0
0.00
0
Rising main (mtr.) 1 3.45 +0
0.00
4
Sewer Line (km.) 1 4.20 +0
0.00
0
STP (MLD) 1 90.00 +0
0.00
27
19 PrayagRaj Prayagraj Interception, Diversion of Balance discharge of 02 drains and 50 MLD STP to Augment existing Treatment Capacity (80 MLD) Naini STP for Sewerage District-A at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 05-Sep-2023 186.47 83.71 5.44 97.32 1 50.00 2 M/s JWIL-SSG (Joint Venture) 95.57 04-Mar-2025 03-Jul-2026 +0.00
3.00
+0.00
5.76
Co-treatment Unit for Fecal Sludge (KLD) 1 20.00 +0
0.00
0 30-Jun-2025
  • LOA issued to JV M/s JWIL and SSG ,New Delhi on 25.11.2024
  • LOA (Amended) issued to JV M/s JWIL and SSG , on dated 17.01.2025
  • Contract Agreement has been signed and Date of Start is 04.03.2025 and Date of Completion 03.07.2026 including 2 months Trial and Run Period
  • Survey, Design and Drawing work is in progress.
  • Soil testing of STP & SPS site has been completed.
  • Firm has requested for amendment in proposed Technology of STP, the same has been rejected by NMCG, New Delhi vide letter no. Pr-12012/22/2022-Tech-1NMCG Dated 27.05.2025
  • BEP has been Approved for 2.90 MLD Bargad Ghat SPS and Structure Drawing are submitted for vetting.
  • BEP of 50 MLD STP was Submitted by Firm and observations on the same were communicated to firm. Firm has submitted revised BEP on 25.06.2025
Firm has requested for change in proposed technology and same was rejected by NMCG, New Delhi. 01-Jan-1900 01-Jan-1900
Interception And Diversion 1 2.00 +0
1.00
0
Rising main (mtr.) 1 0.10 +0
0.00
0
Sewer Line (km.) 1 0.06 +0
1.00
0
SPS (MLD) 2A 1 3.50 +0
4.00
0
STP (MLD) 1 50.00 +0
3.00
4
20 Mathura Mathura Mathura sewerage scheme (I&D and STP Works for balance drain) NGP2-NON EAP HAM 07-Sep-2022 292.56 149.85 9.61 133.10 1 60.00 4 M/s EIEL Mathura Infra Engineers Private Limited 240.01 30-Nov-2024 29-Nov-2026 +1.88
38.16
+0.00
22.85
Interception & Diversion, Sewer Line, MPS and STP 1 1970.00 +0
48.18
0 30-Jun-2025
  • LOA issued to L1 Bidder on on 27.09.2023. CA signed on 12.12.2023. Effective date of start shall be to concessionaire after financial closure.
  • Effective date of start has been given to concessionaire as 30.11.2024.
  • IPS Kala Patthar civil work and its Rising main has been completed
  • SBR basin and MPS construction work is in progress in STP premises.
No Delay- Currently, the actual progress is more than the required. - 30-Nov-2026 30-Nov-2026
Interception And Diversion 1 4.00 +0
25.00
0
IPS (MLD) 2 47.00 +0
32.22
13
MPS (MLD) 1 60.00 +0
65.55
4
Rising main (mtr.) 1 9290.00 +0
74.73
4
STP (MLD) 1 60.00 +0
40.00
4
21 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 29-Jul-2024 240.93 123.45 6.97 110.51 2 42.50 2 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.90 07-Sep-2024 06-Jun-2026 +0.17
14.61
+0.00
107.85
Interception And Diversion 1 1.00 +0
3.00
0 30-Jun-2025
  • Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Construction of Boundary wall work is in progress. SBR Basin-2 Selector Zone wall 4th lift casting completed. CCT wall reinforcement, shuttering and casting work is in progress. MPS - wall 2nd lift casting completed.
  • 39 MLD STP Daulatganj Operation & Maintenance started on dt. 05.11.2024.
Slow progress by firm. L.D. imposed Rs. 66,74,000.00 on firm 06-Jun-2026 06-Jul-2026
MPS 1 3.50 +0
5.50
0
STP (MLD) 2 42.50 +0
62.24
27
Uppgradation of SPS 3 3.00 +0
100.00
0
22 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow NGP DBOT 30-Jan-2023 264.67 137.55 8.53 118.60 1 50.00 3 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.74 14-Jun-2024 13-Mar-2026 +0.00
3.67
+0.00
0.00
Interception And Diversion 1 3.00 +0
3.90
0 30-Jun-2025
  • Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed and handed over to UPJN (Urban). BEP of the STP is approved and design & drawing work is in progress. SBR Basin - Excavation, Dressing & Shoring work is in progress. Design & Drawing of proposed IPS is in progress. Site submerged with sewage water due to leakage of UPJN (Urban) SPS Inlet pipeline.
Slow progress by firm. L.D. imposed Rs. 64,13,000.00 on firm 13-Apr-2026 13-Apr-2026
Rising main (mtr.) 1 3.50 +0
0.00
0
SPS (MLD) 1 22.60 +0
0.00
0
STP (MLD) 1 50.00 +0
4.37
17
23 Ayodhya Faizabad Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) NGP HAM 06-May-2021 221.66 109.03 7.62 105.01 1 33.00 15 M/s Eco Protection Engineer Pvt Ltd 149.47 03-Mar-2023 02-Jan-2025
30-Sep-2024
31-Dec-2024
31-May-2024
+0.00
98.17
+0.00
86.86
Boundary wall (mtr.) 1 200.00 +0
99.90
4 24-Jun-2025
  • Trial run of 33 MLD STP is started.
Effluent Disposal Line (km.) 1 0.06 +0
99.80
4
MPS (MLD) 1 41.60 +0
99.60
4
Rising main (mtr.) 1 0.40 +0
100.00
4
Sewer Line (km.) 1 3.88 +0
98.75
4
STP (MLD) 1 33.00 +0
96.96
5