1 |
Agra |
Agra |
Agra Sewerage Scheme( Interception & diversion and STP works) |
NGP2-EAP |
HAM |
06-May-2020 |
842.25 |
371.29 |
25.40 |
445.56 |
13 |
177.60 |
26 |
M/s AWWMPL Pvt Ltd |
582.84 |
05-Apr-2023 |
04-Apr-2025 |
04-Apr-2025, 31-Dec-2025 |
+0.10
72.89
|
+60.18
332.00
|
20-Aug-2025 |
-
As per pervious meeting discussion, In order to 07 Nos. DSTP forest clearance , Land Gazette notification meeting has been conducted on 02.05.2025 and soon gazette notification will be published and after that stage 2 permission will be applied
-
Component wise progress of Agra (HAM) 100 MLD STP- 68%, WIP 35 MLD STP- 76.2, WIP 31 MLD STP- 76.48%, WIP MPS 03 Nos.- 73%, WIP Rising Main 9.55 Km- 55%%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
-
As per pervious meeting discussion, In order to complete the remaining works of 31 MLD and 35 MLD STP and make them operational as per the prescribed timeline, Direction has been given to firm to complete the works as early as possible by increasing manpower.
|
2 |
Ayodhya |
Faizabad |
Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) |
NGP |
HAM |
06-May-2021 |
221.66 |
109.03 |
7.62 |
105.01 |
1 |
33.00 |
15 |
M/s Eco Protection Engineer Pvt Ltd |
149.47 |
03-Mar-2023 |
02-Jan-2025 |
15-Aug-2025, 30-Sep-2024, 31-Dec-2024, 31-May-2024 |
+0.01
98.32
|
+0.00
97.00
|
18-Aug-2025 |
-
Trial run of 33 MLD STP is started.
|
3 |
Hapur |
Hapur |
I&D and STP works at District-Hapur |
NGP |
DBOT |
19-Sep-2023 |
49.06 |
22.85 |
1.42 |
24.79 |
1 |
6.00 |
1 |
M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV) |
39.28 |
08-Nov-2024 |
07-Feb-2026 |
|
+2.00
10.00
|
+0.71
0.71
|
20-Aug-2025 |
-
Date of start is given on 08.11.24. Date of completion of work is 05.02.2026 to M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV), Reg. Office B-29, IIIrd Floor, RDC Rajnagar, Ghaziabad - 201013. AGREEMENT cost of project is Rs. 39,28,13,617.00.
-
Soil Testing Completed. Boundary Wall work is in progress.
-
The amount of mobilization advance has been claimed by the firm.
-
Land Issue Resolved in Feb 2025.
-
BEP has been submitted by the firm on 11.03.2025. The said BEP has been sent by this Division to the Executive Engineer, Division Office (E/M), Uttar Pradesh Jal Nigam (Rural), Meerut on 15.03.2025. After examining the components related to the equipment in the said office, some observations were found, the details of which have been made available to this Division by (E/M) letter no. 202/Hapur Sewerage/05 dated 05.05.2025. By letter no. 620/Yo-42/12 dated 13.05.2025 of this Division, the firm has been directed to provide revised BEP again.
-
Revised BEP has been submitted by the firm on 06.06.2025. The said BEP has been sent by this Division to the Executive Engineer, Division Office (E/M), Uttar Pradesh Jal Nigam (Rural), Meerut on 09.06.2025
-
BEP and GAD sent for vetting to IIT BHU VARANASI on 19.06.25
|
4 |
Hathras |
Hathras |
I&D and STP works at Hathras Town |
NGP |
DBOT |
30-Jan-2023 |
128.91 |
70.48 |
4.55 |
53.88 |
1 |
24.00 |
10 |
M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd |
119.05 |
06-Sep-2024 |
05-Jun-2026 |
05-Jun-2026 |
+0.00
8.50
|
+5.41
5.41
|
20-Aug-2025 |
-
Date of start is 06.09.2024 and date of completion is 05.06.2024. Survey work is going on.
-
Survey and soil investigation has been completed by firm
-
Project was delayed as the land for STP was handed over in March 2025 by Nagar Palika Parishad Hathras. After that BEP is approved and structural drawings of SBR also vetted by IIT and at present excavation for SBR is in progress
|
5 |
Kanpur Nagar |
Kanpur Nagar |
I&D and STP works at Kanpur-Pankha |
NGP |
HAM |
12-Mar-2018 |
967.23 |
248.39 |
31.05 |
718.84 |
1 |
30.00 |
3 |
M/s Kanpur River Management Pvt. Ltd. |
708.70 |
11-Oct-2019 |
11-Oct-2021 |
29-Feb-2024, 30-Apr-2025, 30-Jun-2025, 30-Sep-2024, 30-Sep-2025, 31-Aug-2024, 31-Jul-2025, 31-Oct-2024 |
+0.00
99.56
|
+0.00
370.19
|
18-Aug-2025 |
-
Panka STP commissioned on dated 24.06.2023. Renovation of 130 MLD STP Jajmau work 96% complete.
|
6 |
Lucknow |
|
Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow |
NGP |
DBOT |
29-Jul-2024 |
240.93 |
123.45 |
6.97 |
110.51 |
2 |
42.50 |
2 |
M/s R.K. Engineers- Khilari Infrastructure (JV) |
187.90 |
07-Sep-2024 |
06-Jun-2026 |
|
+0.00
16.73
|
+1.63
109.48
|
20-Aug-2025 |
-
39 MLD STP Daulatganj Operation & Maintenance started on dt. 05.11.2024.
-
Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Construction of Boundary wall work is in progress. SBR Basin-2 Selector Zone wall 3rd lift reinforcement, shuttering and casting work is in progress. CCT wall 1st lift reinforcement, shuttering and casting work is in progress. MPS - wall 4th lift reinforcement, shuttering and casting work is in progress.
|
7 |
Lucknow |
Lucknow |
Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow |
NGP |
DBOT |
30-Jan-2023 |
264.67 |
137.55 |
8.53 |
118.60 |
1 |
50.00 |
3 |
M/s R.K. Engineers- Khilari Infrastructure (JV) |
187.74 |
14-Jun-2024 |
13-Mar-2026 |
|
+0.00
4.08
|
+1.76
4.26
|
20-Aug-2025 |
-
Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed and handed over to UPJN (Urban). BEP of the STP is approved and design & drawing work is in progress. SBR Basin - Excavation, Dressing & Shoring work is in progress. Design & Drawing of proposed IPS is in progress. Site submerged with sewage water due to leakage of UPJN (Urban) SPS Inlet pipeline. Dewatering work is in progress.
|
8 |
Mathura |
Chhata |
Chhata Town Sewerage Scheme (I&D and STP works), District Mathura |
NGP |
DBOT |
25-Oct-2022 |
56.15 |
34.52 |
2.23 |
19.40 |
1 |
6.00 |
14 |
M/s Shailesh Kumar J.V. |
48.97 |
12-Nov-2024 |
11-Aug-2026 |
|
+0.05
5.65
|
+1.12
1.65
|
20-Aug-2025 |
-
Survey and soil investigation has completed by firm.
-
BEP of STP has been approved.
-
Boundary wall construction work is going on at site.
-
Project is slightly delayed due to problem of water logging at STP Site as PWD, Mathura was constructing a culvert on Kosi Drain and due to diversion of drain the water of kosi drain got obstructed. The STP site is located near to the branch drain of kosi drain at upstream side which got over flowed and leading to water logging at STP Site.This hindrance cleared in march 2025 after that work was resumed.
-
Construction of HTS and staff quarter building is in progress at MPS.
-
STP site is flooded due to overflow from Bahrauli branch drain, (situated near to the site) from 1 month. The current water level at STP site is higher to the HFL, provided by irrigation department. At this situation all works are heavily affected. Not only in present this kind of situation during monsoon will affect the operation and maintenance services in later too.
Due to the current scenario of site, we have sent a letter to SDM, Chhata, requesting a new land for
construction of STP in this project with all requisite details of the scenario of original project site.
-
Date of Start 12.11.2024 has been given to the firm.
|
9 |
Mathura |
Vrindavan |
I&D and 13 MLD STP works at Vrindavan City |
NGP |
DBOT |
25-Oct-2022 |
77.70 |
39.90 |
2.56 |
35.24 |
1 |
13.00 |
2 |
M/s SIMA -G D- N.P. (JV) |
65.86 |
11-Jun-2024 |
10-Mar-2026 |
|
+0.07
60.60
|
+4.20
18.93
|
20-Aug-2025 |
-
LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work is in progress.
-
Work is going in SBR basin, CCT, Admin building, Pannel room, SHU and in MPS units.
-
Kalideh MPS rising main works has been done.
-
STP site is water logged from 10.08.2025, work is affected due to this
|
10 |
Mathura |
Kosi Kalan |
I&D and STP works at Kosi Kalan Town, District Mathura |
NGP |
DBOT |
25-Oct-2022 |
66.59 |
31.24 |
2.03 |
33.32 |
1 |
12.00 |
1 |
M/s R K Engineers Sales Ltd |
53.60 |
16-Oct-2024 |
15-Jul-2026 |
|
+0.10
6.00
|
+1.53
1.53
|
20-Aug-2025 |
-
Ground improvement work of SBR basin is completed, PCC work is in progress.
-
Continous instruction has been given to firm for expediting the work.
-
BEP of STP has been approved.
-
Survey and soil investigation has been done by firm.
-
Boundary wall construction work is going on at site.
-
Preparation for PCC work of SBR basin is in progress, hindered due to rain at site.
-
LOA has been issued on date 18.06.2024 and Date of start has been given 16.10.2024 to the firm. Survey work is going on
|
11 |
Mathura |
Mathura |
Mathura sewerage scheme (I&D and STP Works for balance drain) |
NGP2-NON EAP |
HAM |
07-Sep-2022 |
292.56 |
149.85 |
9.61 |
133.10 |
1 |
60.00 |
4 |
M/s EIEL Mathura Infra Engineers Private Limited |
240.01 |
30-Nov-2024 |
29-Nov-2026 |
|
+0.55
43.48
|
+24.46
70.84
|
20-Aug-2025 |
-
LOA issued to L1 Bidder on on 27.09.2023. CA signed on 12.12.2023. Effective date of start shall be to concessionaire after financial closure.
-
Effective date of start has been given to concessionaire as 30.11.2024.
-
IPS Kala Patthar civil work and its Rising main has been completed
-
SBR basin and MPS construction work is in progress in STP premises.
|
12 |
Meerut |
Meerut |
I&D and STP works at Meerut |
NGP2-EAP |
HAM |
06-May-2020 |
690.71 |
363.78 |
26.31 |
280.19 |
1 |
220.00 |
2 |
M/s. Meerut STP Pvt. Ltd. |
369.74 |
11-Nov-2024 |
10-Nov-2026 |
|
+0.08
31.43
|
+1.48
110.57
|
20-Aug-2025 |
-
. Payment for1st and 2nd MS have been released
-
BEP, Layout and HFD approved for 220 MLD STP, 2 I&D’s & MPS, BEP of Treated Effluent Pipeline from Lohia Nagar STP to Outfall pending with Concessionaire, BEP of EPS and Pipeline pending with Concessionaire.
GAD, Structural Design and Dwg. for Admin Building, SBR, CCT, Tonner Room approved
QAP, Date Sheet and GAD of Decanter, Diffuser approved, QAP, Date Sheet and GAD of Air Blowers under review., Vortex Grit Remover approved by PE.
GAD of Primary Clarifier approved by UPJN. , QAP, Date Sheet and GAD of Chlorination System pending with Concessionaire.
QAP of Filter Belt Press pending with Concessionaire., Revised QAP of Pumps to be submitted by Concessionaire. Revised GAD of MPS pending with Concessionaire.
-
Work in progress at only 1 front of STP, Concessionaire need to open multiple working fronts.
Inadequate Manpower deployment at site, Manpower deployment to be increased.
|
13 |
Moradabad |
Moradabad |
Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 |
NGP |
HAM |
23-Jul-2018 |
118.69 |
53.53 |
3.52 |
61.64 |
1 |
25.00 |
5 |
Moradabad STP Pvt Ltd |
113.85 |
20-Jan-2023 |
19-Jan-2025 |
19-Jan-2025, 30-Jun-2025 |
+0.00
95.00
|
+1.76
55.95
|
20-Aug-2025 |
-
03 milestones have been completed and 95% progress is achieved of project
-
Review meeting under chairmanship of MD sir on dated 28.05.2025 were held to expedite work
-
Completion of MPS plugging & inlet chamber due to high Sub-soil water level.
-
Meeting held under chairmanship of JMD sir on 06 may 2025 to expedite the progress on remaining structure & activity
-
EOT has been sent to NMCG for necessary perusal
-
Delay due to flooding condition at site due to back water from Ramganga river flooding
-
Delay due to not starting work at multiple fronts
-
Deployment of Inadequate manpower at site, manpower deployment to be increased
-
Payment of Electricity connection yet to be received
|
14 |
PrayagRaj |
Prayagraj |
Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode |
NGP |
DBOT |
14-Mar-2023 |
331.75 |
180.27 |
11.22 |
140.27 |
1 |
43.00 |
13 |
M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) |
204.40 |
19-Mar-2024 |
18-Aug-2025 |
|
+1.13
68.25
|
+0.00
66.21
|
18-Aug-2025 |
-
Column work is under Progress for Admin Building.
-
Ground Floor and 1st Floor Slab completed for STP Staff Quarter. Balance work is under Progress
-
Compound wall for Sitaram Ghat SPS is under Progress.
-
Casting of 9th Lift of Wall at AB Culvert SPS has been completed. Compound wall & Sinking work is under progress.
-
2200 m laying of Rising main completed. Balance Laying is under progress
-
TEPS Slab Casting work is completed .Brick work and plaster is under Progress
-
Slab work for Sludge Dewatering Unit is under progress.
-
Basic Engineering Package has been vetted by IIT Delhi and same approved by UPJN (R)
-
GAD & RCC Design and Drawings of CCT, SBR Unit and Amitabh Bachhan Culvert SPS has been vetted by IIT Delhi and approved by UPJN (R)
-
RCC work for PTU is completed. Walk way and connecting channel is under Progress.
-
RCC work for MCC Room ,Chlorination room & Air Blower is completed. RCC work for chlorine tonner yard is under Progress.
-
Outer wall of all SBR Basin of STP is completed up to 90 % and partian wall is under progress.
-
RCC of CCT Unit of STP is completed.
|
15 |
PrayagRaj |
Prayagraj |
Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode |
NGP |
DBOT |
27-Jan-2023 |
475.98 |
242.85 |
15.24 |
217.89 |
1 |
90.00 |
7 |
M/s Triveni Engineering and Industries |
309.74 |
24-Aug-2024 |
23-Feb-2026 |
|
+0.00
38.50
|
+0.00
31.44
|
18-Aug-2025 |
-
Excavation, PCC and Raft of CCT is completed & steel binding work of Wall is in progress.
-
Excavation, foundation and column work upto lintel level of workshop is completed, balance work is in progress.
-
Excavation & raft of TEPH completed & 1st lift of Wall is completed. Balance work is in progress.
-
Earth work, PCC, Footing foundation and column upto plinth beam work of Air Blower Building is completed and balance work is in progress.
-
Earth work, PCC work and Raft footing is completed of Inlet Chamber is and Column work is in progress.
-
Shifting of Existing Rising main inside Mumfordganj SPS Campus work is in progress.
-
Work is interrupted due to water level increased of river Ganga.
-
Survey, Design and Drawing work is in progress
-
Contract Agreement has been executed.
-
860 m laying of Gravity main (Sadar Bazar) & 350 m laying of Gravity main (Sankar Ghat) completed Balance Laying is under progress.
-
Excavation, PCC, Grit Slab and Wall Raft of SBR & Wall 1st & 2nd Lift is completed & Wall 3rd Lift is in progress.
-
Date of Start 24.08.2024 and Date of Completion 23.02.2026 including 3 month of Trial and run has been given to the firm M/s Triveni Engineering and Industries Limited.
-
Survey, Design and Drawing work is in progress
-
2850 m laying of Rising main completed. Balance Laying is under progress
-
Excavation, PCC, Grit Slab and Wall Raft of SBR is completed & Wall 1st Lift is in progress.
-
Excavation, PCC and Raft of CCT is completed & steel binding work of Wall is in progress.
|
16 |
PrayagRaj |
Prayagraj |
Interception, Diversion of Balance discharge of 02 drains and 50 MLD STP to Augment existing Treatment Capacity (80 MLD) Naini STP for Sewerage District-A at Prayagraj Uttar Pradesh under DBOT mode |
NGP |
DBOT |
05-Sep-2023 |
186.47 |
83.71 |
5.44 |
97.32 |
1 |
50.00 |
2 |
M/s JWIL-SSG (Joint Venture) |
95.57 |
04-Mar-2025 |
03-Jul-2026 |
|
+0.00
3.44
|
+0.00
5.76
|
18-Aug-2025 |
-
LOA issued to JV M/s JWIL and SSG ,New Delhi on 25.11.2024
-
Contract Agreement has been signed and Date of Start is 04.03.2025 and Date of Completion 03.07.2026 including 2 months Trial and Run Period
-
Survey, Design and Drawing work is in progress.
-
Soil testing of STP & SPS site has been completed.
-
Firm has requested for amendment in proposed Technology of STP, the same has been rejected by NMCG, New Delhi vide letter no. Pr-12012/22/2022-Tech-1NMCG Dated 27.05.2025
-
BEP has been Approved for 2.90 MLD Bargad Ghat SPS and Structure Drawing are submitted for vetting.
-
BEP of 50 MLD STP was Submitted by Firm and observations on the same were communicated to firm. Firm has submitted revised BEP on 25.06.2025
-
LOA (Amended) issued to JV M/s JWIL and SSG , on dated 17.01.2025
|
17 |
Shamli |
Banat |
I&D and STP Work in Banat, Shamli |
NGP |
DBOT |
25-May-2023 |
48.71 |
24.93 |
1.58 |
22.20 |
1 |
5.00 |
3 |
M/s R K Engineers Sales Ltd |
37.92 |
14-Oct-2024 |
13-Jan-2026 |
|
+0.20
16.40
|
+0.39
1.31
|
20-Aug-2025 |
-
Project is 4 months behind schedule.
-
Delay in design/drawing submission by Contractor.
-
Contractor need to increase expedite the progress of work and submission of design/drawings.
-
GAD, Structural Design and Dwg. for SHU approved
-
GAD, Structural design and drawing of I&D Structure approved
-
GAD and Data Sheet of Diffuser and decanter approved
-
GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
-
Approach Road and boundary wall work in progress
-
GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
-
Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
-
BEP, Layout and HFD approved for 05 MLD STP.
-
Survey and Soil investigation work completed
|
18 |
Shamli |
Bantikhera Banat |
I&D and STP Work in Bantikhera and Babri village, Shamli |
NGP |
DBOT |
25-May-2023 |
55.47 |
29.41 |
1.84 |
24.22 |
1 |
5.00 |
1 |
M/s R K Engineers Sales Ltd |
41.91 |
14-Oct-2024 |
13-Jan-2026 |
|
+0.00
5.00
|
+0.59
1.38
|
20-Aug-2025 |
-
BEP, Layout and HFD approved for 05 MLD STP.
-
Work halted due to unresolved land dispute.
-
Project is 7 months behind schedule.
-
Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
-
Survey and Soil investigation work completed
|
19 |
Shamli |
Shamli |
I&D and STP Work in Shamli |
NGP |
DBOT |
25-May-2023 |
206.02 |
103.19 |
6.66 |
96.17 |
1 |
40.00 |
1 |
M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) |
120.92 |
14-Oct-2024 |
13-Jan-2026 |
|
+0.30
19.10
|
+0.00
7.65
|
18-Aug-2025 |
-
Contractor need to increase expedite the progress of work and submission of design/drawings.
-
GAD, Structural Design and Dwg. for SHU approved
-
GAD, Structural Design and Dwg. of I&D Structure approved
-
GAD and Data sheet of Decanter and diffuser approved
-
GAD, Structural Design and Dwg. for Admin. Building & Lab approved
-
Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
-
Approach Road and Boundary wall work in progress
-
BEP, Layout and HFD approved for 40 MLD STP.
-
GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
-
GAD for Admin Building and Sludge Handling and Dewatering Building Submitted, which clear for Vetting & Structural Design.
-
CCT and I&D GAD Submitted, which clear for Vetting & Structural Design.
-
Project is 4 months behind schedule.
-
Delay in design/drawing submission by Contractor.
|
20 |
Shamli |
Thanabhawan |
I&D and STP Work in Thanabhawan, Shamli |
NGP |
DBOT |
25-May-2023 |
97.19 |
55.63 |
3.50 |
38.06 |
1 |
10.00 |
5 |
M/s R K Engineers Sales Ltd |
63.72 |
14-Oct-2024 |
13-Jan-2026 |
|
+0.30
15.30
|
+0.85
2.60
|
20-Aug-2025 |
-
Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
-
Survey and Soil investigation work completed
-
Approach Road work in progress
-
Delay in design/drawing submission by Contractor.
-
Contractor need to increase expedite the progress of work and submission of design/drawings.
-
GAD, Structural Design and Dwg. for SHU approved
-
Project is 4 months behind schedule.
-
BEP, Layout and HFD approved for 10 MLD STP.
-
GAD, Structural Design and Dwg. for SBR and Boundary wall approved.
-
GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.
-
CCT GAD were Submitted, which clear for Vetting & Structural Design.
-
Boundary Wall work in progress
|
21 |
Unnao |
Shuklaganj |
I&D of Drains and STP works in Shuklaganj (05MLD) |
NGP |
HAM |
28-Jul-2017 |
65.18 |
25.93 |
1.90 |
37.35 |
1 |
5.00 |
5 |
M/s KRMPL Kanpur |
38.87 |
11-Oct-2019 |
10-Jul-2021 |
10-Jul-2021, 13-Jun-2023, 14-Dec-2022, 30-Apr-2025, 30-Aug-2025, 30-Jun-2025, 30-Nov-2025, 30-Sep-2025, 31-Aug-2024, 31-Dec-2025, 31-Jan-2025 |
+2.00
86.00
|
+0.00
23.47
|
18-Aug-2025 |
-
Total 7 drains are discharging into River Ganga in NPP Shuklaganj out of which 5 drains of discharge 4.66 MLD has to be Intercepted & Diverted to under Construction 5 MLD STP Shuklaganj and rest of the 02 drains of discharge 7.3 MLD has to be tapped & treated by U.P. J.N. (Urban) under SBM 2 programme. There are 86 manpower engaged by KRMPL, for Civil work 56manpower in different Structure PTU, Admin Building, Air Blower, & Boundary wall work and 30 manpower engaged in Electrical & Mechanical work Progress. In consideration of the cash flow concerns affecting the project progress, if required, special advance may also given to the Concessionaire. – A proposal of advance of Rs. 6.50 Cr. (2.00 Cr. For Unnap STP & Rs. 4.5 Cr. For Shuklaganj STP) against extra work amounting to Rs. 9.50 Cr. was sent to NMCG against which a tripartite agreement has been signed between NMCG, UPJN(R) and M/s KRMPL to provided Special Interest-Bearing Advance to firm for expediting the work and against it an amount of Rs. 3.18 Cr. has been paid as an advance to firm. I&D and STP works at Unnao is ongoing under Namami Gange, likely to be completed by Sept-25
|
22 |
Unnao |
Unnao |
I&D of Drains and STP works in Unnao (15MLD) |
NGP |
HAM |
28-Jul-2017 |
102.20 |
43.73 |
3.22 |
55.25 |
1 |
15.00 |
1 |
M/s KRMPL Kanpur |
68.68 |
11-Oct-2019 |
10-Jul-2021 |
10-Jul-2021, 15-Mar-2023, 15-May-2025, 15-Oct-2022, 15-Sep-2021, 25-Feb-2022, 30-Apr-2023, 30-Jun-2024, 30-Jun-2025, 30-May-2025, 30-Nov-2025, 30-Sep-2025, 31-Dec-2024, 31-Dec-2025, 31-Jul-2024, 31-Mar-2025, 31-Oct-2025 |
+0.00
98.00
|
+0.00
52.01
|
18-Aug-2025 |
-
1200 mm RCC Pipe 384.80meter work laying out of 399.80 meter sewer line is done balance 15.00 meter work in progress, KRMPL deployed 10 manpower at site. Dewatering & cleaning of 543.45 meter work in progress (518.45 meter done) balance 25.00 meter work in progress KRMPL deployed cleaning of Sewer line 12 manpower. STP operating daily from 11.1.2025 through temporary line but CCT is not functional till date due to commissioning of CCT WORK IS PENDING from KRMPL also material short fall PAD HEATER & Pressure switch. In consideration of the cash flow concerns affecting the project progress, if required, special advance may also given to the Concessionaire. – A proposal of advance of Rs. 6.50 Cr. (2.00 Cr. For Unnap STP & Rs. 4.5 Cr. For Shuklaganj STP) against extra work amounting to Rs. 9.50 Cr. was sent to NMCG against which a tripartite agreement has been signed between NMCG, UPJN(R) and M/s KRMPL to provided Special Interest-Bearing Advance to firm for expediting the work and against it an amount of Rs. 3.18 Cr. has been paid as an advance to firm. I&D and STP works at Unnao is ongoing under Namami Gange, likely to be completed by Sept-25
|
23 |
Varanasi |
Varanasi |
I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi |
NGP |
DBOT |
19-Oct-2022 |
308.09 |
97.62 |
7.81 |
172.94 |
1 |
55.00 |
2 |
M/s Enviro Infra Engineers limited MTS JV |
151.55 |
07-Mar-2024 |
06-Dec-2025 |
|
+1.00
76.00
|
+0.00
54.21
|
18-Aug-2025 |
-
BEP submitted by firm to which observation have been raised. compliance pending.
-
Soil testing done. Team mobilized at site.
-
Meeting held under chairmanship of APD Sir on 20.06.2024 to resolve issues of design/drawing. Firm submitted BEP of STP only on 24.06.2024
-
Vetting of process flow of STP and MPS done by IIT-BHU. Structural drawing awaited. Preparatory works in progress
-
Raft of SBR basin completed. Wall work in progress
-
RCC framework of MCC, air blower, DG yard and transformer yard completed.
-
Laying of Rising main pipe line in progress
-
Laying of Effluent pipe line in progress
|