Sr. No. District Name Agency Name Scheme Code Scheme Name Covered Villages Covered Habitations Covered Population Base Year Intermediate Year Design Year Contract Completion Date Actual Completion Date Trial Run Date O&M Start Date TPI Fill Status TPI Remark EE Status EE Remark View
1 Muzaffarnagar Gayatri Projects LTD 20058590 BIRALASI WATER SUPPLY SCHEME 1 2 6793 2022 2037 2052 16-Sep-2022 07-Oct-2024 08-Oct-2024 09-Oct-2024 The details given by the contractor are correct at the time of approval. View
2 Muzaffarnagar Gayatri Projects LTD 20022067 Dinkarpur 1 1 3691 2022 2037 2053 16-Sep-2022 25-Sep-2023 25-Dec-2023 26-Dec-2023 The details given by the contractor are correct at the time of approval. OK View
3 Muzaffarnagar Gayatri Projects LTD 20022206 ILLAHBANS 1 1 3500 2022 2037 2052 16-Sep-2022 06-Oct-2023 06-Jan-2024 07-Jan-2024 The details given by the contractor are correct at the time of approval. View
4 Muzaffarnagar Gayatri Projects LTD 20058586 KAKRA WATER SUPPLY SCHEME CHANDPUR BASDHARA (PART I) 1 2 8670 2022 2037 2052 16-Sep-2022 02-Aug-2024 02-Aug-2024 03-Aug-2024 The details given by the contractor are correct at the time of approval. OK View
5 Muzaffarnagar Gayatri Projects LTD 20098069 KANHAERI GP RO WSS 2 2 3452 2023 2038 2053 16-Sep-2022 14-Jan-2024 14-Apr-2024 15-Apr-2024 The details given by the contractor are correct at the time of approval. OK View
6 Muzaffarnagar Gayatri Projects LTD 20022997 KAZI KHERA RO WSS 1 2 5417 2022 2037 2052 16-Sep-2022 25-Oct-2023 25-Jan-2024 26-Jan-2024 The details given by the contractor are correct at the time of approval. OK View
7 Muzaffarnagar Gayatri Projects LTD 20098206 KHATAULI GRAMIN GP RO WSS 2 2 18171 2023 2038 2053 16-Sep-2022 01-Dec-2024 01-Mar-2025 02-Mar-2025 The details given by the contractor are correct at the time of approval. View
8 Muzaffarnagar Gayatri Projects LTD 20022187 Muhammadpur Rai Singh 1 1 5710 2022 2037 2052 16-Sep-2022 08-Dec-2023 10-Mar-2024 11-Mar-2024 The details given by the contractor are correct at the time of approval. View
9 Muzaffarnagar Gayatri Projects LTD 20022918 MUNDBHAR RO WSS 1 2 5545 2022 2037 2052 16-Sep-2022 03-Jun-2024 03-Sep-2024 04-Sep-2024 The details given by the contractor are correct at the time of approval. View
10 Muzaffarnagar Gayatri Projects LTD 20023355 MUNDBHAR RO WSS (BHORA KHURD WSS) 1 4 4439 2022 2037 2052 16-Sep-2022 29-Jan-2024 29-Apr-2024 30-Apr-2024 The details given by the contractor are correct at the time of approval. View
11 Muzaffarnagar Gayatri Projects LTD 20098063 RATHUR GP RO WSS 1 1 1771 2023 2038 2053 16-Sep-2022 02-Dec-2024 02-Mar-2025 03-Mar-2025 The details given by the contractor are correct at the time of approval. View
12 Muzaffarnagar Gayatri Projects LTD 20022060 Roni harjipur 1 1 8632 2023 2038 2053 04-Feb-2024 05-Nov-2023 05-Feb-2024 06-Feb-2024 The details given by the contractor are correct at the time of approval. OK View
13 Muzaffarnagar Gayatri Projects LTD 20098062 SHEKHPURA GP RO WSS 1 2 11818 2023 2038 2053 16-Sep-2022 07-Oct-2024 08-Jan-2025 09-Jan-2025 The details given by the contractor are correct at the time of approval. OK View
14 Muzaffarnagar Gayatri Projects LTD 20098064 SHOROM GP RO WSS 1 2 9276 2023 2038 2053 16-Sep-2022 02-Dec-2024 21-Jun-2025 22-Jun-2025 The details given by the contractor are correct at the time of approval. View
15 Muzaffarnagar Gayatri Projects LTD 20098066 SHUKRATAL GP RO WSS 2 2 24542 2023 2038 2053 16-Sep-2022 01-Oct-2024 31-Dec-2024 01-Jan-2025 The details given by the contractor are correct at the time of approval. OK View