| 1 |
Muzaffarnagar |
Gayatri Projects LTD |
20058590 |
BIRALASI WATER SUPPLY SCHEME |
1 |
2 |
6793 |
2022 |
2037 |
2052 |
16-Sep-2022 |
07-Oct-2024 |
08-Oct-2024 |
09-Oct-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
|
View
|
| 2 |
Muzaffarnagar |
Gayatri Projects LTD |
20022067 |
Dinkarpur |
1 |
1 |
3691 |
2022 |
2037 |
2053 |
16-Sep-2022 |
25-Sep-2023 |
25-Dec-2023 |
26-Dec-2023 |
|
The details given by the contractor are correct at the time of approval. |
|
OK |
View
|
| 3 |
Muzaffarnagar |
Gayatri Projects LTD |
20022206 |
ILLAHBANS |
1 |
1 |
3500 |
2022 |
2037 |
2052 |
16-Sep-2022 |
06-Oct-2023 |
06-Jan-2024 |
07-Jan-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
|
View
|
| 4 |
Muzaffarnagar |
Gayatri Projects LTD |
20058586 |
KAKRA WATER SUPPLY SCHEME CHANDPUR BASDHARA (PART I) |
1 |
2 |
8670 |
2022 |
2037 |
2052 |
16-Sep-2022 |
02-Aug-2024 |
02-Aug-2024 |
03-Aug-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
OK |
View
|
| 5 |
Muzaffarnagar |
Gayatri Projects LTD |
20098069 |
KANHAERI GP RO WSS |
2 |
2 |
3452 |
2023 |
2038 |
2053 |
16-Sep-2022 |
14-Jan-2024 |
14-Apr-2024 |
15-Apr-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
OK |
View
|
| 6 |
Muzaffarnagar |
Gayatri Projects LTD |
20022997 |
KAZI KHERA RO WSS |
1 |
2 |
5417 |
2022 |
2037 |
2052 |
16-Sep-2022 |
25-Oct-2023 |
25-Jan-2024 |
26-Jan-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
OK |
View
|
| 7 |
Muzaffarnagar |
Gayatri Projects LTD |
20098206 |
KHATAULI GRAMIN GP RO WSS |
2 |
2 |
18171 |
2023 |
2038 |
2053 |
16-Sep-2022 |
01-Dec-2024 |
01-Mar-2025 |
02-Mar-2025 |
|
The details given by the contractor are correct at the time of approval. |
|
|
View
|
| 8 |
Muzaffarnagar |
Gayatri Projects LTD |
20022187 |
Muhammadpur Rai Singh |
1 |
1 |
5710 |
2022 |
2037 |
2052 |
16-Sep-2022 |
08-Dec-2023 |
10-Mar-2024 |
11-Mar-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
|
View
|
| 9 |
Muzaffarnagar |
Gayatri Projects LTD |
20022918 |
MUNDBHAR RO WSS |
1 |
2 |
5545 |
2022 |
2037 |
2052 |
16-Sep-2022 |
03-Jun-2024 |
03-Sep-2024 |
04-Sep-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
|
View
|
| 10 |
Muzaffarnagar |
Gayatri Projects LTD |
20023355 |
MUNDBHAR RO WSS (BHORA KHURD WSS) |
1 |
4 |
4439 |
2022 |
2037 |
2052 |
16-Sep-2022 |
29-Jan-2024 |
29-Apr-2024 |
30-Apr-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
|
View
|
| 11 |
Muzaffarnagar |
Gayatri Projects LTD |
20098063 |
RATHUR GP RO WSS |
1 |
1 |
1771 |
2023 |
2038 |
2053 |
16-Sep-2022 |
02-Dec-2024 |
02-Mar-2025 |
03-Mar-2025 |
|
The details given by the contractor are correct at the time of approval. |
|
|
View
|
| 12 |
Muzaffarnagar |
Gayatri Projects LTD |
20022060 |
Roni harjipur |
1 |
1 |
8632 |
2023 |
2038 |
2053 |
04-Feb-2024 |
05-Nov-2023 |
05-Feb-2024 |
06-Feb-2024 |
|
The details given by the contractor are correct at the time of approval. |
|
OK |
View
|
| 13 |
Muzaffarnagar |
Gayatri Projects LTD |
20098062 |
SHEKHPURA GP RO WSS |
1 |
2 |
11818 |
2023 |
2038 |
2053 |
16-Sep-2022 |
07-Oct-2024 |
08-Jan-2025 |
09-Jan-2025 |
|
The details given by the contractor are correct at the time of approval. |
|
OK |
View
|
| 14 |
Muzaffarnagar |
Gayatri Projects LTD |
20098064 |
SHOROM GP RO WSS |
1 |
2 |
9276 |
2023 |
2038 |
2053 |
16-Sep-2022 |
02-Dec-2024 |
21-Jun-2025 |
22-Jun-2025 |
|
The details given by the contractor are correct at the time of approval. |
|
|
View
|
| 15 |
Muzaffarnagar |
Gayatri Projects LTD |
20098066 |
SHUKRATAL GP RO WSS |
2 |
2 |
24542 |
2023 |
2038 |
2053 |
16-Sep-2022 |
01-Oct-2024 |
31-Dec-2024 |
01-Jan-2025 |
|
The details given by the contractor are correct at the time of approval. |
|
OK |