Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in

Project Completion Certificate Details

Sr. No. District Name Agency Name Scheme Code Scheme Name Covered Villages Covered Habitations Covered Population Base Year Intermediate Year Design Year Contract Completion Date Actual Completion Date Trial Run Date O&M Start Date TPI Fill Status TPI Remark EE Status EE Remark View
1 Amethi Gayatri Projects LTD 20072844 BAISARA WATER SUPPLY SCHEME 2 13 2938 2022 2037 2052 13-Mar-2025 07-Sep-2024 05-Dec-2024 10-Mar-2025 Hardcopy submiited and all documents found okay.. View
2 Amethi Gayatri Projects LTD 20085728 BANHAPUR WATER SUPPLY SCHEME 2 4 2431 2023 2038 2052 22-Sep-2024 07-Jun-2024 10-Sep-2024 21-Dec-2024 Hardcopy submitted and found okay as per the submitted documents.. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance View
3 Amethi Gayatri Projects LTD 20100938 BHAVALPUR & AMBARPUR WATER SUPPLY SCHEME 3 16 4698 2022 2037 2053 25-Jun-2025 02-Sep-2024 05-Dec-2024 15-Mar-2025 Hardcopy submitted and found okay as per the submitted documents.. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
4 Amethi Gayatri Projects LTD 20072845 Daranagar & Sewara GP water supply scheme 2 7 4800 2022 2037 2052 10-Aug-2024 14-Jun-2024 14-Sep-2024 15-Dec-2024 Hardcopy submitted and found okay as per the submitted documents. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
5 Amethi Gayatri Projects LTD 20099327 ISMAILPUR WATER SUPPLY SCHEME 3 5 2799 2022 2037 2052 24-Nov-2024 17-Jun-2024 19-Sep-2024 28-Nov-2024 Hardcopy submitted and found okay as per the submitted documents.. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance View
6 Amethi Gayatri Projects LTD 20034334 Jainagara water supply scheme 1 2 1850 2022 2037 2052 03-Nov-2024 02-Jun-2024 05-Sep-2024 10-Dec-2024 Hardcopy submitted and found okay as per the submitted documents.. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
7 Amethi Gayatri Projects LTD 20085725 JAMALPUR RAMPUR & TARAUNA WATER SUPPLY SCHEME 2 16 4652 2022 2037 2052 12-Jul-2024 07-Jun-2024 08-Jun-2024 15-Dec-2024 All Document not provided by EPC hence returns to the EPC All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
8 Amethi Gayatri Projects LTD 20085825 KAIMA WATER SUPPLY SCHEME 1 7 2762 2022 2037 2052 22-Mar-2025 14-Sep-2024 20-Dec-2024 10-Mar-2025 Hardcopy submitted and found okay as per the submitted documents.. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
9 Amethi Gayatri Projects LTD 20034270 Kharawa water supply scheme 2 8 3349 2022 2037 2052 06-May-2024 09-Jun-2024 15-Sep-2024 11-Nov-2024 Hardcopy submitted and found okay as per the submitted documents.. All things are found satisfactory in this Scheme , finalized for Operation And Maintenance View
10 Amethi Gayatri Projects LTD 20034318 Mahaiya Senduriya water supply scheme 1 6 5499 2022 2037 2052 03-May-2024 16-Jun-2024 19-Sep-2024 26-Nov-2024 Hardcopy submitted and found okay as per the submitted documents.. All things are found satisfactory in this Scheme , finalized for Operation And Maintenance View
11 Amethi Gayatri Projects LTD 20098295 MAWAIYA RAHMAT GARH WATER SUPPLY SCHEME 1 11 9186 2022 2037 2052 27-Jun-2025 10-Jun-2024 11-Sep-2024 15-Dec-2024 Hardcopy submitted and found okay as per the submitted documents.. Hardcopy submitted and found okay as per the submitted documents.. View
12 Amethi Gayatri Projects LTD 20077657 Mayas & Nimi Water Supply Scheme 2 10 4230 2022 2037 2057 10-Aug-2024 27-Jun-2024 29-Sep-2024 18-Dec-2024 All Document not provided by EPC hence returns to the EPC All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
13 Amethi Gayatri Projects LTD 20076489 NABHANPUR WATER SUPPLY SCHEME 2 7 3007 2022 2037 2052 14-Mar-2025 15-Jun-2024 19-Sep-2024 25-Dec-2024 Hardcopy submiited and all documents found okay.. View
14 Amethi Gayatri Projects LTD 20101996 NADIWAN WATER SUPPLY SCHEME 1 13 3024 2022 2037 2052 27-Jun-2025 07-Sep-2024 13-Dec-2024 15-Mar-2025 Hardcopy submitted and found okay as per the submitted documents. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
15 Amethi Gayatri Projects LTD 20101987 PAIGA WATER SUPPLY SCHEME 1 5 1248 2022 2037 2052 26-Nov-2025 25-Jun-2024 26-Sep-2024 15-Nov-2024 Hardcopy submitted and found okay as per the submitted documents.. All things are found satisfactory in this Scheme , finalized for Operation And Maintenance View
16 Amethi Gayatri Projects LTD 20072819 Peeparpur & Naugirwan GP water supply scheme 2 6 2689 2022 2037 2052 13-Aug-2024 25-Jun-2024 29-Sep-2024 16-Nov-2024 Hardcopy submitted and found okay as per the submitted documents.. All things are found satisfactory in this Scheme , finalized for Operation And Maintenance View
17 Amethi Gayatri Projects LTD 20035177 PINDARA PARERA WATER SUPPLY SCHEME 1 11 4328 2022 2037 2052 03-Nov-2024 15-May-2024 20-Aug-2024 01-Dec-2024 Hardcopy submitted and found okay as per the submitted documents.. All things are found satisfactory in this Scheme , finalized for Operation And Maintenance View
18 Amethi Gayatri Projects LTD 20034985 RAMAE WATER SUPPLY SCHEME 1 4 3002 2022 2037 2052 06-May-2025 21-Jun-2024 24-Sep-2024 06-Nov-2024 Hardcopy submitted and found okay as per the submitted documents.. All things are found satisfactory in this Scheme , finalized for Operation And Maintenance View
19 Amethi Gayatri Projects LTD 20076471 RAMPUR CHAUDHARI & ALIPUR WATER SUPPLY SCHEME 2 10 3234 2022 2037 2052 22-Mar-2025 02-Sep-2024 05-Dec-2024 10-Mar-2025 Hardcopy submitted and found okay as per the submitted documents. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
20 Amethi Gayatri Projects LTD 20102462 RASOOLABADH WATER SUPPLY SCHEME 1 14 5536 2022 2037 2052 27-Jun-2024 03-Jun-2024 06-Sep-2024 15-Dec-2024 Hardcopy submitted and found okay as per the submitted documents.. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance View
21 Amethi Gayatri Projects LTD 20098293 SADIPUR WATER SUPPLY SCHEME 1 3 2882 2022 2037 2052 27-May-2025 07-Sep-2024 13-Dec-2024 15-Mar-2025 Hardcopy submitted and found okay as per the submitted documents.. All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... View
22 Amethi Gayatri Projects LTD 20085858 TRILOKPUR WATER SUPPLY SCHEME 2 7 3423 2023 2038 2053 13-Sep-2024 10-Apr-2024 20-Jul-2024 25-Nov-2024 Hardcopy submitted All things found satisfactory in the Scheme and finalized for Operation And Maintenance View
23 Amethi Gayatri Projects LTD 20099387 VATIYA WATER SUPPLY SCHEME 1 1 2173 2022 2037 2052 27-Nov-2024 07-Jun-2024 11-Sep-2024 15-Jan-2025 Hardcopy submitted and found okay as per the submitted documents.. All things are found satisfactory in this Scheme , finalized for Operation And Maintenance View