| 1 |
Amethi |
Vindhya-GAJA (JV) |
20085692 |
ANI BAIJAL WATER SUPPLY SCHEME |
1 |
5 |
3687 |
2023 |
2038 |
2053 |
29-Apr-2024 |
14-Aug-2024 |
15-Nov-2024 |
16-Feb-2025 |
|
Hardcopy submiited and all documents found okay.. |
|
Hardcopy submitted and found okay as per the submitted documents.. |
View
|
| 2 |
Amethi |
Vindhya-GAJA (JV) |
20085680 |
ARGWAN & SAKRAWA WATER SUPPLY SCHEME |
4 |
8 |
4459 |
2023 |
2038 |
2053 |
28-Apr-2024 |
20-Jun-2024 |
20-Sep-2024 |
21-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance... |
View
|
| 3 |
Amethi |
Vindhya-GAJA (JV) |
20066626 |
ASNI1 WATER SUPPLY SCHEME |
1 |
3 |
2728 |
2023 |
2038 |
2053 |
06-Jan-2024 |
19-Jun-2024 |
19-Sep-2024 |
20-Dec-2024 |
|
All Document not provided by EPC hence returns to the EPC |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 4 |
Amethi |
Vindhya-GAJA (JV) |
20066413 |
babu pur Sharia water supply Scheme |
1 |
5 |
3301 |
2023 |
2038 |
2053 |
06-Jan-2024 |
12-Nov-2024 |
12-Feb-2025 |
13-May-2025 |
|
All Document not provided by EPC hence returns to the EPC |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 5 |
Amethi |
Vindhya-GAJA (JV) |
20065721 |
BADAGAON WATER SUPPLY SCHEME |
1 |
5 |
4132 |
2023 |
2038 |
2053 |
09-Jan-2023 |
04-Jun-2024 |
04-Sep-2024 |
05-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 6 |
Amethi |
Vindhya-GAJA (JV) |
20066484 |
BADALGARH & BAKHTWARNAGAR WATER SUPPLY SCHEME |
1 |
8 |
3510 |
2023 |
2038 |
2053 |
06-Jan-2024 |
14-May-2024 |
13-Sep-2024 |
14-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
Hardcopy submitted and found okay as per the submitted documents.. |
View
|
| 7 |
Amethi |
Vindhya-GAJA (JV) |
20098342 |
BANDOIYA Water Supply Scheme |
1 |
2 |
1498 |
2023 |
2038 |
2053 |
04-Jul-2024 |
26-Jun-2024 |
26-Sep-2024 |
27-Dec-2024 |
|
All Document not provided by EPC hence returns to the EPC |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 8 |
Amethi |
Vindhya-GAJA (JV) |
20085694 |
BASAIKPUR WATER SUPPLY SCHEME |
1 |
6 |
2135 |
2023 |
2038 |
2053 |
29-Apr-2024 |
05-Nov-2024 |
05-Feb-2025 |
06-May-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance |
View
|
| 9 |
Amethi |
Vindhya-GAJA (JV) |
20085686 |
BEHTA MURTAJAPUR WATER SUPPLY SCHEME |
3 |
5 |
2777 |
2023 |
2038 |
2053 |
29-Apr-2024 |
25-May-2024 |
26-Sep-2024 |
05-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
Hardcopy submitted and found okay as per the submitted documents.. |
View
|
| 10 |
Amethi |
Vindhya-GAJA (JV) |
20085677 |
BHATGAWAN WATER SUPPLY SCHEME |
2 |
9 |
5311 |
2023 |
2038 |
2053 |
29-Apr-2024 |
17-Dec-2024 |
17-Mar-2025 |
18-Jun-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 11 |
Amethi |
Vindhya-GAJA (JV) |
20070881 |
BIKHANPUR WATER SUPPLY SCHEME |
1 |
6 |
2031 |
2023 |
2038 |
2053 |
23-Mar-2024 |
19-Jun-2024 |
19-Sep-2024 |
20-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 12 |
Amethi |
Vindhya-GAJA (JV) |
20085683 |
CHANDAIPUR WATER SUPPLY SCHEME |
2 |
7 |
2835 |
2023 |
2038 |
2053 |
29-Apr-2024 |
18-Jun-2024 |
18-Sep-2024 |
19-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 13 |
Amethi |
Vindhya-GAJA (JV) |
20070878 |
GAIMAU WATER SUPPLY SCHEME |
1 |
6 |
1965 |
2023 |
2038 |
2053 |
23-Mar-2024 |
07-Jun-2024 |
07-Sep-2024 |
08-Dec-2024 |
|
All Document not provided by EPC hence returns to the EPC |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 14 |
Amethi |
Vindhya-GAJA (JV) |
20068067 |
GANGAULI & GHAGUGHAR WATER SUPPLY SCHEME |
1 |
13 |
4152 |
2023 |
2038 |
2053 |
23-Mar-2023 |
20-Jun-2024 |
20-Sep-2024 |
21-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 15 |
Amethi |
Vindhya-GAJA (JV) |
20101973 |
GARHA MAFI WATER SUPPLY SCHEME |
1 |
6 |
1883 |
2023 |
2038 |
2053 |
04-Jul-2024 |
13-Nov-2024 |
13-Feb-2025 |
13-May-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 16 |
Amethi |
Vindhya-GAJA (JV) |
20068335 |
GARTHOLIYA & LOHANG PUR WATER SUPPLY SCHEME |
2 |
13 |
4186 |
2023 |
2038 |
2053 |
08-Feb-2024 |
06-Jun-2024 |
06-Sep-2024 |
07-Dec-2024 |
|
d All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 17 |
Amethi |
Vindhya-GAJA (JV) |
20066597 |
JARAUTA VILLAGE WATER SUPPLY SCHEME |
2 |
8 |
2614 |
2023 |
2038 |
2053 |
06-Jan-2024 |
08-Nov-2024 |
08-Feb-2025 |
09-May-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 18 |
Amethi |
Vindhya-GAJA (JV) |
20101945 |
JETHU MAWAI WATER SUPPLY SCHEME |
1 |
2 |
1248 |
2023 |
2038 |
2053 |
04-Jul-2024 |
06-Nov-2024 |
06-Feb-2025 |
07-May-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 19 |
Amethi |
Vindhya-GAJA (JV) |
20068372 |
KANAK SINGHPUR & KORARI HEERSHAH WATER SUPPLY SCHEME |
2 |
7 |
3844 |
2023 |
2038 |
2053 |
23-Mar-2024 |
10-Nov-2024 |
10-Feb-2025 |
11-May-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 20 |
Amethi |
Vindhya-GAJA (JV) |
20066620 |
KANKOO PUR WATE SUPPLY SCHEME |
1 |
5 |
2406 |
2023 |
2038 |
2053 |
17-Feb-2024 |
22-Jun-2024 |
22-Sep-2024 |
23-Dec-2024 |
|
All Document not provided by EPC hence returns to the EPC |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 21 |
Amethi |
Vindhya-GAJA (JV) |
20070858 |
KANOO WATER SUPPLY SCHEME |
1 |
14 |
2176 |
2023 |
2038 |
2053 |
07-Feb-2024 |
24-Jun-2024 |
27-Sep-2024 |
28-Dec-2024 |
|
All Document not provided by EPC hence returns to the EPC |
|
. |
View
|
| 22 |
Amethi |
Vindhya-GAJA (JV) |
20065165 |
KAPURIPUR Water Supply Scheme |
2 |
8 |
2387 |
2022 |
2038 |
2052 |
17-Feb-2024 |
07-May-2024 |
10-Aug-2024 |
13-Nov-2024 |
|
Hardcopy submitted |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 23 |
Amethi |
Vindhya-GAJA (JV) |
20066590 |
KASARA&PATAPUR VILLAGE WATER SUPLLY SCHEME |
2 |
19 |
3847 |
2023 |
2038 |
2053 |
06-Jan-2024 |
09-Nov-2024 |
09-Feb-2025 |
10-May-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 24 |
Amethi |
Vindhya-GAJA (JV) |
20070889 |
KOHRA WATER SUPPLY SCHEME |
1 |
13 |
5091 |
2023 |
2038 |
2053 |
08-Feb-2023 |
16-Dec-2024 |
16-Mar-2025 |
17-Jun-2025 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 25 |
Amethi |
Vindhya-GAJA (JV) |
20070871 |
KORARI GIRDHAR SHAH WATER SUPPLY SCHEME |
1 |
10 |
3130 |
2023 |
2038 |
2053 |
08-Feb-2023 |
22-Dec-2024 |
23-Mar-2025 |
16-Jun-2025 |
|
d All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 26 |
Amethi |
Vindhya-GAJA (JV) |
20085690 |
KOTWAR MAU WATER SUPPLY SCHEME |
1 |
8 |
1969 |
2023 |
2038 |
2053 |
29-Apr-2024 |
21-Jun-2024 |
21-Sep-2024 |
22-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 27 |
Amethi |
Vindhya-GAJA (JV) |
20101948 |
LAUKAPUR WATER SUPPLY SCHEME |
1 |
1 |
1395 |
2023 |
2038 |
2053 |
04-Jul-2024 |
29-Jun-2024 |
29-Sep-2024 |
30-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
Hardcopy submitted and found okay as per the submitted documents.. |
View
|
| 28 |
Amethi |
Vindhya-GAJA (JV) |
20100650 |
MAHESH PUR WATER SUPPLY SCHEME |
1 |
2 |
1632 |
2023 |
2038 |
2053 |
24-Apr-2024 |
18-Dec-2024 |
08-Mar-2025 |
09-Jun-2025 |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 29 |
Amethi |
Vindhya-GAJA (JV) |
20066548 |
MANJH GAON WATER SUPPLY SCHEME |
1 |
6 |
2534 |
2023 |
2038 |
2053 |
07-Jan-2024 |
12-May-2024 |
04-Sep-2024 |
16-Dec-2024 |
|
Hardcopy submitted |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 30 |
Amethi |
Vindhya-GAJA (JV) |
20068981 |
NARHARPUR WATER SUPPLY SCHEME |
1 |
4 |
2270 |
2023 |
2038 |
2053 |
23-Mar-2024 |
26-Jun-2024 |
26-Sep-2024 |
27-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
Hardcopy submitted and found okay as per the submitted documents.. |
View
|
| 31 |
Amethi |
Vindhya-GAJA (JV) |
20085670 |
NEWADA KISUNPUR GARH WATER SUPPLY SCHEME |
2 |
13 |
3882 |
2023 |
2038 |
2053 |
27-Mar-2023 |
22-Jun-2024 |
22-Sep-2024 |
23-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 32 |
Amethi |
Vindhya-GAJA (JV) |
20067969 |
NIHAL GARH SAIDA PATTI WATER SUPPLY SCHEME |
2 |
6 |
2006 |
2023 |
2038 |
2053 |
22-Mar-2024 |
22-Jun-2024 |
23-Sep-2024 |
24-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
Hardcopy submitted and found okay as per the submitted documents.. |
View
|
| 33 |
Amethi |
Vindhya-GAJA (JV) |
20065222 |
Paniyar Water Supply Scheme |
5 |
17 |
4114 |
2023 |
2038 |
2053 |
17-Feb-2024 |
15-Jun-2025 |
15-Sep-2024 |
16-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 34 |
Amethi |
Vindhya-GAJA (JV) |
20068382 |
PARSOYIA WATER SUPPLY SCHEME |
2 |
10 |
2541 |
2023 |
2038 |
2053 |
23-Mar-2024 |
27-Jun-2024 |
27-Sep-2024 |
28-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 35 |
Amethi |
Vindhya-GAJA (JV) |
20098338 |
PURAB DWARA Water Supply Scheme |
1 |
3 |
1541 |
2023 |
2038 |
2053 |
04-Jul-2024 |
11-Nov-2024 |
11-Feb-2025 |
10-May-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 36 |
Amethi |
Vindhya-GAJA (JV) |
20098321 |
PURE MIHIB SHAH Water Supply Scheme |
2 |
7 |
3000 |
2023 |
2038 |
2053 |
04-Jul-2024 |
05-Jun-2024 |
05-Sep-2024 |
06-Dec-2024 |
|
All Document not provided by EPC hence returns to the EPC |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 37 |
Amethi |
Vindhya-GAJA (JV) |
20067991 |
PURE PAHAL WAN WATER SUPPLY SCHEME |
2 |
14 |
2088 |
2023 |
2038 |
2053 |
07-Feb-2024 |
22-Jun-2024 |
22-Sep-2024 |
23-Dec-2024 |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance. |
View
|
| 38 |
Amethi |
Vindhya-GAJA (JV) |
20085696 |
SAITHA WATER SUPPLY SCHEME |
1 |
19 |
5011 |
2023 |
2038 |
2053 |
29-Apr-2024 |
30-Jun-2025 |
15-Mar-2025 |
16-Jun-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 39 |
Amethi |
Vindhya-GAJA (JV) |
20068050 |
SANAHA WATER SUPPLY SCHEME |
1 |
2 |
2680 |
2023 |
2038 |
2053 |
01-Jun-2024 |
05-Nov-2024 |
09-Sep-2024 |
12-Aug-2024 |
|
Hardcopy submitted |
|
All Things Are Found Satisfactory , Scheme is Finalized For Operation and Maintenance |
View
|
| 40 |
Amethi |
Vindhya-GAJA (JV) |
20068350 |
SANGRAMPUR & GOOJIPUR WATER SUPPLY SCHEME |
3 |
18 |
5465 |
2023 |
2038 |
2053 |
23-Mar-2024 |
30-Jun-2025 |
12-Mar-2025 |
13-Jun-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 41 |
Amethi |
Vindhya-GAJA (JV) |
20070856 |
SARIYA DUBAAN WATER SUPPLY SCHEME |
1 |
9 |
2190 |
2023 |
2033 |
2053 |
07-Feb-2024 |
23-Dec-2024 |
23-Mar-2025 |
09-Jun-2025 |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 42 |
Amethi |
Vindhya-GAJA (JV) |
20066500 |
SAUNA WATER SUPPLY SCHEME |
1 |
4 |
2965 |
2023 |
2038 |
2053 |
22-Dec-2023 |
29-Dec-2024 |
29-Mar-2025 |
30-Jun-2025 |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 43 |
Amethi |
Vindhya-GAJA (JV) |
20101943 |
SINGTHEE WATER SUPPLY SCHEME |
1 |
4 |
1290 |
2023 |
2038 |
2053 |
04-Jul-2024 |
16-Jun-2024 |
16-Sep-2024 |
17-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
Hardcopy submitted and found okay as per the submitted documents.. |
View
|
| 44 |
Amethi |
Vindhya-GAJA (JV) |
20065731 |
SONARI KALAN & AMTAHI WATER SUPPLY SCHEME |
2 |
19 |
7074 |
2023 |
2038 |
2053 |
09-Jan-2024 |
07-Dec-2024 |
07-Mar-2025 |
08-Jun-2025 |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
View
|
| 45 |
Amethi |
Vindhya-GAJA (JV) |
20067972 |
SONARI KANOO WATER SUPPLY SCHEME |
2 |
18 |
2474 |
2023 |
2038 |
2053 |
08-Feb-2024 |
18-Jun-2024 |
18-Sep-2024 |
19-Dec-2024 |
|
d All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 46 |
Amethi |
Vindhya-GAJA (JV) |
20068083 |
TARA PUR WATER SUPPLY SCHEME |
2 |
5 |
1719 |
2023 |
2038 |
2053 |
29-Apr-2024 |
07-Nov-2024 |
07-Feb-2025 |
09-May-2025 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All things are found satisfactory in this Scheme , finalized for Operation And Maintenance |
View
|
| 47 |
Amethi |
Vindhya-GAJA (JV) |
20098333 |
TENWASI Water Supply Scheme |
1 |
5 |
1731 |
2023 |
2038 |
2053 |
24-Apr-2024 |
27-Dec-2024 |
27-Mar-2025 |
28-Jun-2025 |
|
All things found satisfactory in the Scheme and finalized for Operation And Maintenance |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 48 |
Amethi |
Vindhya-GAJA (JV) |
20098346 |
Tikariya Water Supply Scheme |
1 |
13 |
2451 |
2023 |
2038 |
2053 |
16-May-2023 |
16-Dec-2024 |
16-Mar-2025 |
17-Jun-2025 |
|
Hardcopy submitted and found okay as per the submitted documents. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance.. |
View
|
| 49 |
Amethi |
Vindhya-GAJA (JV) |
20066641 |
UTTARGAON WATER SUPPLY SCHEME |
1 |
16 |
3726 |
2023 |
2038 |
2053 |
06-Jan-2024 |
15-Jun-2024 |
15-Sep-2024 |
16-Dec-2024 |
|
Hardcopy submitted and found okay as per the submitted documents.. |
|
All Things Found Satisfactory Scheme is Finalized for Operation and Maintenance |
View
|